Cork City Traveller Accommodation Programme 2025 - 2029

Item 3 As outlined in Table 11 Cork City Council have planning permission or proposals (some involving AHB) to deliver 54 – 63 Group Housing units in the short to medium term – the delivery of this development is carried over from TAP 2019-2024 (ref Section 7.1 Measure 1, 2, 3, 5). However, while it is estimated in Table 15 that 44 units are required to meet the existing requirement, a further 24 units will be required to meet future projected need during the TAP 2025-2029 period. While the traditional model for delivering Group Housing Schemes will substantially deliver upon this target, it is considered that it is unlikely to deliver it fully within this timeframe. It is proposed therefore that this shortfall be addressed through 2-6 clustered housing provision within or co- located with Council or AHB housing schemes as discussed in Item 1 and 2.

Table 18 TAP 2025-2029 Item 3

66

Cork City Council | Traveller Accommodation Programme 2025-2029