CE Management Report October 2021

Schemes at Contract Award (to go to construction Q4 2021)

Scheme

No. of Units

Status

Denroches Cross

43

At contract award stage

Glen Ryan Road

9

At contract award stage

Old Mallow Road

54

At contract award stage

Total:

106

Regeneration Schemes

Scheme

No. of Units

Status

Phase 2B – At tender review stage. Stage 4 Submission November 2021.

CNWQR

38

Phase 1C – At tender review stage. Stage 4 Submission November 2021.

CNWQR

41

Phase 1D West – Croppy Boy – AHB (Tuath) development of 21 units commenced construction in November 2019 with 7 units delivered in June 2020. Remaining units to be delivered in 2021. Phase 1D East - Planning granted for Affordable Housing to be delivered by O Cualann AHB (17 units). Enabling works to commence Q1 2022.

CNWQR

21

CNWQR

17

Phase 3B – Stage 2 submission made to DHLGH. Part 8 to be advertised December 2021.

CNWQR

62

Phase 4A – Stage 2 submission made to DHLGH. Part 8 to be advertised December 2021.

CNWQR

43

Total:

222

Capital Assistance Scheme (Construction schemes in planning)

Scheme

No. of units

Status

Respond - St Vincent’s Convent, St. Mary's Road

25

Pre-planning underway

Total:

25

25