CE Management Report January 2021

Green Lane, Blackpool

112

Enabling Works underway.

Dec-22

Part V and Turnkeys across the city

141

Construction underway.

Various

Coach Street

12

Contract awarded.

Mar-22

Spring Lane

8

Construction underway.

May-22

Shankiel

20

Contract awarded.

May-22

Watercourse Road

37

Construction underway.

Mar-22

Montenotte

27

Contract awarded.

Oct-22

Total:

1258

Capital Assistance Scheme (Construction)

No. of units

Scheme

Status

25

Pre-planning underway.

Respond - St Vincent’s Convent, St. Mary's Road

Total:

25

Regeneration Schemes

Scheme

No. of Units

Status

CNWQR 2B

38

Phase 2B – Due to be tendered in March 2021.

CNWQR

41

Phase 1C – Due to be tendered in March 2021.

CNWQR

21

Phase 1D West – The AHB development of 21 units commenced construction in November 2019 and 7 units have been delivered in June 2020.

CNWQR

17

Phase 1D East - Planning application submitted for Affordable Housing to be delivered by O Cualann AHB (17 units). Estimated on site by July 2021.

CNWQR

62

Phase 3B – Progress to part 8 by May 2021

CNWQR

43

Phase 4A – Progress to Part 8 by May 2021

CNWQR

24

Phase 2C – under construction. Estimate Substantial Completion June 2021

Total:

246