Construction Detail
Appraisal of Construction Phase Environmental Effects
Normal Speed Stations
Fast Speed Stations
Potential for Ancillary Electrical Infrastructural Development? Indication of type and size of potential ancillary electrical development
Limited need for any ancillary electrical infrastructural development. At a regional level the ESB Network and supply of electricity to the Cork area will need to be enhanced to meet the planned population/ employment growth of
Some potential upgrade to existing substations required, however these works will form an integral part of the delivery of the EV chargers. At a regional level the ESB Network and supply of electricity to the Cork area will need to be enhanced to meet the planned population/ employment growth of
the city region as envisaged in the National Planning Framework
the city region as envisaged in the National Planning Framework
Indication of Maximum Footprint of Development Works
35m 2
125m 2