CCC CDP 2022-2028 2 Year Progress Report

[ Cork City Development Plan 2022-2028, Section 15(2) Two-Year Progress Report ]

The table below and map in Figure 73 present the relevant data.

Figure 72: Planning Permissions in Hinterland Settlements

Reference

Location

No. of Units

Wastewater (WW)

94 units, 2 commercial units, 1 retail unit, 1 creche 43 units, pharmacy, 5 medical consulting room

22/40976 ABP-314905-22

Upper Leemount, Kerry Pike Former Sunset Ridge Hotel, Killeens

Public Sewer

22/41247

Public Sewer

22/41547 ABP-317376-23

Rathpeacon, Killeens

5 dwelling houses

Public Sewer

Domestic WW treatment unit

23/41970

Rathpeacon, Killeens

1 dwelling house

22/40950 ABP-314892-22

Killeens

2 dwelling houses

Public Sewer

2 domestic WW treatment units

23/41761

Kiln Road, Killeens

2 dwelling houses

23/41703

Rathpeacon, Killeens Ballinvriskig, Upper Glanmire Ballinvriskig, Upper Glanmire Ballinvriskig, Upper Glanmire Ballinvriskig, Upper Glanmire Ballinvriskig, Upper Glanmire Ballinvriskig, Upper Glanmire

10 dwelling houses

Public Sewer

Ros Ard WWTP with capacity for 35 houses Ros Ard WWTP with capacity for 35 houses

22/41343

8 dwelling houses

21/40745 ABP-315701-23 23/42355 ABP-319011-24 23/42356 ABP-319018 -24 23/42357 ABP-319028-24 23/42358 ABP-319025-24

20 residential dwellings

1 dwelling house

Public Sewer

1 dwelling house

Public Sewer

1 dwelling house

Public Sewer

1 dwelling house

Public Sewer

189 residential units

TOTAL

The review of these permissions confirms that objective 10.96 has broadly been adhered to.

Uisce Éireann states that the capacity of the wastewater treatment plant (WWTP) in Upper Glanmire has available capacity for 35 houses. This capacity will be breached once all dwellings associated with planning permission references 22/41343 (24 houses) and 21/40745 (20 houses) are built. Uisce Éireann states that a development of more than 35 houses would require upgrade works to the WWTP. This capacity constraint will affect future applications within the Development Plan period. Uisce Éireann states that there is no spare capacity available at present at the WWTP for development in Killeens. While the granted development in Killeens has been accommodated by Uisce Éireann, connections for future development may be unavailable. It is also noted that permission for 96 units, in combination with other construction development in Kerry Pike, was found to exceed the 10% threshold in the Development Plan, however An Bord Pleanála found that the proposal had regard to the scale and character of the village and had access to public water, and therefore was considered to be in keeping with Objective 10.96.

144