CE Management Report January 2022

[CE Management Report] _________________________________________________________________________________________________________________

Schemes in the Course of Planning

Scheme

Status

No. Of Units

Bramble Cottages

4

Part 8 approved

Glenamoy Lawn

3

Part 8 approved

Errigal Heights

28

Part 8 approved

Foyle Avenue (Incl Ardmore Avenue)

2

Stage 4 submitted to the DHLGH January 2022.

Madonna House - Phase 2

6

Part 8 approved

Poulavone, Ballincollig

64

Target date for tender is February 2022

Kerry Road (Sli Gartan), Mayfield

1

Part 8 approved Tenders due back Jan 2022

Boyce Street Phase 2

37

Part 8 Approved

Hollywood Estate

7

Part 8 approved

Redemption Heights

64

Part 8 stage

Cloverhill Court

88

Part 8 application Q2 2022

Westside

41

Part 8 application Q1 2022

Churchfield Road

21

Post planning design

Total:

366