Construction underway Phased Delivery from Q1 2021
Redforge Road (AHB: Respond)
80
Dec-21
Corkeran’s Quay
3
Construction underway
Dec-22
Phase 2C – CNWQR
24
Construction completing
22
Dec-21 with interim phasing
Boherboy Road
153
Construction underway
Enabling works complete. Main contract at tender stage
Gerald Griffin Street/Burkes Avenue
49
Jun-23
Construction underway. Enabling Works complete
Respond – Thomas Davis Street
28
Dec-22
Boyces Street Phase 1
14
Construction underway
May 23
Enabling Works completed. Construction underway
Green Lane, Blackpool (AHB: Cluid)
112
Dec-22
Springville House (AHB: Tuath: Downsizing)
35
Construction underway
Jan-22
Coach Street
12
Construction underway
Mar-22
Spring Lane
8
Construction underway
Mar-22
Shanakiel
20
Construction underway
Sept 22
Watercourse Road
37
Construction underway
Sept -22
Montenotte – Affordable Housing Scheme
27
Construction underway
Oct-22
Montenotte – Social Housing (Tuath)
27
Construction underway
Oct-22
Pouladuff Road
11
Construction underway
Jul-22
Heathfield Ballincollig (Part V)
21
Under Construction
Phased delivery
Ballinglanna (Later phases)
27
Under Construction
Phased delivery
Evergreen Road (AHB: Respond)
28
Under Construction
Sept-22
Former Glenanaar Bar (AHB: Respond)
27
Under Construction
Sept-22
Part V and Turnkeys across the city
245
Construction underway. (Pre-Contract)
Various
Barrack Street
32
Under Construction
Apr-23
Wood Street
16
Under Construction
Nov-23
Cluain Ard, Blarney (Part V)
10
Construction completing
Heathfield, Ballincollig (Part V)
8
Construction completing
Coppengers Field Ballyvolane (Part V)
7
Construction completing
Skehard Road
16
Under Construction
May-22
Sarsfield Road/Doughcloyne
65
Construction underway
Phased delivery
Sunview (Downsizing)
25
Construction underway
Oct-22
Hawkes Road, Bishopstown
64
Construction underway
Aug-23
Old Mallow Road
54
Construction underway
Jul-23
23
Powered by FlippingBook