CE Management Report April 2020.pdf

Planning Decisions confirmed by An Bord Pleanála

9

120%

8

100%

100%

7

6

80%

5

63%

60%

60%

4

50%

3

40%

2

20%

1

0

0%

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Decisions - 2019

Decisions - 2020

Sum of % Confirmed - 2019

Sum of % Confirmed - 2020

Housing Directorate Housing Progress Report April 2020

Schemes in Construction:

Scheme

No. of Units

Completed to date

Balance Status

Estimated Completion

Phase 1B - CNWQR

29

29

0

Construction completed.

Nov-17

Sheridan Park

28

28

0

Construction completed.

Feb-17

Marble Lane, Ballinlough

4

4

0

Construction completed.

Jan-18

Galtan CLG – Construction completed.

124 Lower Glanmire Road

4

4

0

Jan-18

Galtan CLG – Construction completed.

2 St. Joseph’s Villas

4

4

0

Jul-18

Galtan CLG – Construction completed.

1 Montenotte View

3

3

0

Jul-18

Galtan CLG – 3 units completed in 2018, 1 remaining to be delivered 2019.

166 Sundays Well Road

4

3

1

Dec-19

Sheridan Court

3

3

0

Construction completed.

Feb-18

Church Road

43

43

0

Construction completed.

Oct-18

Ard Aoibhinn, Mayfield

5

5

0

Construction completed.

Oct-18

-Phase 1

37-39 Dublin St

5

5

0

Construction completed.

Aug-18

19