CE Management Report April 2020.pdf

Leeside Apartments

78

78

0

Construction completed.

Mar-19

5/6 Shandon St/9 John Philpott Curran St

9

0

9

Construction underway.

Dec-20

Construction underway – Respond.

St. Joachim and Annes

8

0

8

Nov 20

Construction underway – Respond.

Coolroe, Ballincollig

44

0

44

Dec-20

Woodfield, Blarney

18

0

18

Construction underway.

Jul-20

Carrs Hill

36

0

36

Construction underway.

May-20

Castletreasure

2

0

2

Construction underway.

Nov-19

Construction complete – Clúid Housing Association.

Togher Cross, Lehenaghmore

9

9

0

Nov-19

Tuath Housing Association – Construction complete.

Maryborough Ridge

52

52

0

Dec-19

Ballinure Road

5

0

5

Construction underway.

Sept-20

Boyces Street

51

0

51

Construction underway.

Nov-22

Ballinlough Road

6

6

0

Construction completed.

Nov-19

Gearneys Boreen

3

3

0

Practical completion.

Dec-19

Lower Glanmire Road

8

8

0

Galtan CLG.

Dec-19

Sept-20

Boherboy Road

153

0

153

Construction underway.

(Phase 1)

Blackrock Villas

5

5

0

Construction completed.

Dec-19

The Ferns, Ballincollig

4

4

0

Construction completed.

Dec-19

Respond – Thomas Davis Street

28

0

28

Construction underway.

Dec-21

Enabling Works to commenced March 2020.

Green Lane, Blackpool

112

0

112

2022

Maryborough Ridge

29

29

0

Construction completed.

Dec-19

Part V and Turnkeys across the city

112

0

112

Construction underway.

Various

Total:

1477

632

845

Regeneration/Remedial Works Schemes

Scheme

No. of Units Status

CNWQR

38

Phase 2B – Part 8 approved by Council October 2018. Due to be tendered in May 2020.

CNWQR

41

Phase 1C – Part 8 approved by Council October 2018. Due to be tendered in May 2020.

21