CE Management Report June 2020.pdf

Litter Fines to May

140

120

100

80

60

40

20

0

Jan

Feb

Mar

Apr

May

Jun

Court Prosecutions

Issued

Paid

Prosecutions Lost

Prosecutions Taken

Prosecutions Won

Infrastructure Projects __________________________________________________________________________________________________ Roads Capital Programme: TII Funded Projects:

N40 SARSFIELD & BANDON ROAD FLYOVER PROJECT (€31.55 million) L ocalised settlement issues on the N40 continue to be monitored. SIAC Ltd has completed significant repairs. The Maintenance Contract for the N40 has now passed to Egis Lagan and TII.

LOWER GLANMIRE ROAD RESURFACING & FOOTPATH REPAIR CONTRACT (€2.5 million) Construction is substantially complete with some minor works such as lining, signage and cycle protection measures to be installed in the coming weeks.

WESTERN ROAD RESURFACING AND FOOTPATH REPAIR CONTRACT (€700K) Construction tender documents are under development.

Roads Capital Programme: NTA Funded Projects:

CORK CYCLE NETWORK: PHASE 3 – BALLYVOLANE INCLUDING FOX & HOUNDS JUNCTION (€4.0 million) Consultants appointed. Option assessment and data collection underway. SKEHARD ROAD - PHASE 2 PARKHILL TO CHURCH ROAD JUNCTION INCLUDING CSO JUNCTION (€3.5 million) Construction contract is complete.

SKEHARD ROAD- PHASE 3 CHURCH ROAD TO BESSBORO JUNCTION (€2 million) Tender assessment s tage.

DENNEHY’S CROSS TO WILTON GARDENS (€4 million) Preliminary design is complete. Part 8 planning proposals were not approved. Discussions are ongoing with the NTA concerning the delivery of the complete corridor project as part of the Cork Bus Connects Project PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 1 (Mahon to Docklands) (€2.5 million) Preliminary Design is complete. Part 8 Planning is approved. Detailed design process is underway. Site investigation contract is complete. Construction tender scheduled to be published in Q4 2020.

PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 2 (Mahon to Passage) (€4.0 million) Design Team appointment complete.

LEHENAGHMORE ROAD WIDENING & REALIGNMENT PROJECT Preliminary design layout drawings are under development. Land acquisition will be required. Detailed Design Team appointed.

CLARKE’S HILL Preliminary Design and Part 8 planning is complete. Land Acquisition discussions are underway.

10

Powered by