CE Management Report August 2020.pdf

Housing Directorate HOUSING PROGRESS REPORT AUGUST 2020

Schemes in Construction

Status *Estimated completion dates may change due to Covid-19

Estimated Completion Date

Scheme

No Units

Aspen Drive

29

Completed

-

Blarney Street

25

Completed

-

Phase 2A

47

Completed

-

St John’s Well

6

Completed

-

Deanrock

66

Completed

-

White Street

43

At practical completion

-

High Street

9

At practical completion

-

Farranferris

86

Tuath – construction underway

Dec-20

Corcoran’s Quay

3

Construction underway.

Oct-21

Construction underway - Respond.

Millerd Street

25

Sep-20

Carrs Hill

36

Construction underway.

Sep-20

29 & 30 Lower John Street

17

Construction underway.

Dec-20

Woodfield, Blarney

18

Construction underway.

Jul-20

Phase 2C – CNWQR

24

Construction underway.

Dec-20

Grattan Street -Good Shepherd Cork

33

Construction underway.

Aug-20

Gerald Griffin Street

13

Construction underway.

Dec-20

Ballinure Road

5

Construction underway.

Oct-20

Dec-21 with interim phasing

Boherboy Road

153

Construction underway.

Construction underway – Respond.

St. Joachim and Annes

8

Nov-20

Construction underway - Phase 2/2

166 Sundays Well Road

1

Dec-20

Construction underway - Respond.

Redforge Road

80

Dec-21

5/6 Shandon St/9 John Philpott Curran St

9

Construction underway.

Dec-20

18