Construction underway – Respond.
Coolroe, Ballincollig
44
Dec-20
Gerald Griffin Street/Burkes Avenue
Enabling works complete. Main contract at tender stage
43
Sep-22
Respond – Thomas Davis Street
28
Construction underway.
Dec-21
Boyces Street
51
Construction underway.
Nov-22
Green Lane, Blackpool
112
Enabling Works underway.
Dec-22
Part V and Turnkeys across the city
141
Construction underway.
Various
Total:
1155
Regeneration Schemes
Scheme
No. of Units
Status
CNWQR
38
Phase 2B – Part 8 approved by Council October 2018. Due to be tendered in October 2020.
CNWQR
41
Phase 1C – Part 8 approved by Council October 2018. Due to be tendered in October 2020.
CNWQR
38
Phase 1D – Construction is ongoing for the Private/AHB delivery of voluntary housing (21 units). Planning permission in place for Affordable Housing to be delivered by AHB (17 units).
CNWQR
62
Phase 3B – Preparing Part 8 design for Stage 2 submission Phase 4A – Preparing Part 8 design for Stage 2 submission
CNWQR
43
Total:
222
Schemes in the Course of Planning
Scheme
No. Of Units
Status
Springville House
35
Part 8 approved. To be progressed by Tuath Housing Association. Funding submission made to DHPLG.
Barrack Street
32
At contract award stage.
Wood Street
16
At contract award stage.
Bramble Cottages
5
Part 8 application to be prepared.
Glenamoy Lawn
3
Part 8 application to be prepared.
Errigal Heights
32
Part 8 application to be prepared.