LEHENAGHMORE ROAD WIDENING & REALIGNMENT PROJECT Preliminary design layout drawings are under development. Land acquisition will be required. Detailed Design Team appointed.

CLARKE’S HILL Preliminary Design and Part 8 planning is complete. Land Acquisition discussions are underway.

COACH HILL Preliminary layout design is under development.

MAHON TO CITY CENTRE TRANSPORT CORRIDOR (€5 million) will be delivered as part of bus connects

EXISTING NORTHERN RING ROAD ENHANCEMENT PROJECT will be delivered as apart of bus connects

CITY CENTRE PUBLIC TRANSPORT IMPROVEMENT SCHEME (€5 million) Construction is complete. Final Account discussions are ongoing.

MCCURTAIN STREET PUBLIC TRANSPORT IMPROVEMENT SCHEME (€8 million) . Part 8 public consultation has been completed. Submissions now being assessed and draft report for council being prepared.

SOUTH QUAYS PUBLIC TRANSPORT IMPROVEMENT SCHEME (€4.5 million) Consultants appointed. Data collection and option assessment is ongoing.

GRANGE TO TVP PEDESTRIAN & CYCLEWAY inc. N40 Bridge detailed design is underway. Contractor for ground investigation contract appointed, works due to commence shortly.

THOMAS DAVIS BRIDGE JUNCTION IMPROVEMENT SCHEME (€450K) Construction works are complete- signalised junctions now in operation.

SOUTH DOUGLAS ROAD JUNCTION draft Part 8 design documents currently being finalised with scheme to go to public consultation beginning of October.

BALLYBRACK CYCLE SCHEME Part 8 planning approval in place. Tender process for appointment of consultants for detailed design is underway

PEDESTRIAN SAFETY INTERVENTIONS 2019 (€500K) construction completed.

PEDESTRIAN SAFETY INTERVENTIONS 2020 (€500K) Section 38’s were approved by council for new schemes at Vicar’s Road, Dublin Hill, Ringmahon Road and Rathmore Road. Detailed design is being finalised and will go to tender shortly.

NORTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT Tender process for procurement of the route selection design team is underway. Design Team appointment scheduled for Q4 2020.

SOUTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT Tender process for procurement of the route selection design team is underway. Design Team appointment scheduled for Q4 2020.

CURAHEEN TO CARRIGROHANE FOOTPATH AND CYCLE PATH UPGRADE (600k) detailed design is underway.

Roads Capital Programme: CCC Funded Projects:

ST MARY’S CAMPUS works under construction.

HARBOUR VIEW ROAD JUNCTION UPGRADE appointment of contractor is underway and works to commence shortly.

DEANROCK Tender assessment underway. Construction scheduled to commence in Q4 .