Housing Directorate HOUSING PROGRESS REPORT October 2020

Schemes in Construction

Status *Estimated completion dates may change due to Covid-19

Estimated Completion Date

Scheme

No Units

Aspen Drive

29 25 47

Completed Completed Completed Completed Completed Completed Completed

- - - - - - -

Blarney Street

Phase 2A

St John’s Well

6

Deanrock

66 43

White Street High Street

9

Tuath – phased delivery underway Construction underway. Construction underway - Respond. Construction underway. Construction underway. Construction underway. Construction underway.

Farranferris

86

Dec-20

Corcoran’s Quay

3

Apr-21

Millerd Street

25

Sep-20

Carrs Hill

36 17 18 24

Sep-20 Dec-20

29 & 30 Lower John Street

Woodfield, Blarney Phase 2C – CNWQR

Jul-20

Dec-20

Grattan Street -Good Shepherd Cork

33

Construction underway.

Aug-20

Gerald Griffin Street

13

Construction underway. Construction underway.

Dec-20 Dec-20

Ballinure Road

5

Dec-21 with interim phasing

Boherboy Road

153

Construction underway.

Construction underway – Respond.

St. Joachim and Annes

8

Nov-20

Construction underway - Phase 2/2

166 Sundays Well Road

1

Dec-20

Construction underway - Respond.

Redforge Road

80

Dec-21

5/6 Shandon St/9 John Philpott Curran St

9

Construction underway.

Dec-20

Construction underway – Respond.

Coolroe, Ballincollig

44

Dec-20

Gerald Griffin Street/Burkes Avenue Respond – Thomas Davis Street

Enabling works complete. Main contract at tender stage Construction underway. Construction underway. Enabling Works underway.

42

Sep-22

28 51

Dec-21 Nov-22 Dec-22

Boyces Street

Green Lane, Blackpool

112

Part V and Turnkeys across the city

141

Construction underway.

Various

Total:

1,154