CE Management Report October 2020.pdf

Regeneration Schemes Scheme

No. of Units Status

CNWQR

38

Phase 2B – Part 8 approved by Council October 2018. Due to be tendered in late 2020. Phase 1C – Part 8 approved by Council October 2018. Due to be tendered in late 2020. Phase 1D – Planning permission in place for Private/AHB delivery of voluntary housing (21 units) – Under construction. Planning permission in place for Affordable Housing to be delivered by AHB (17 units). Phase 3B – Preparing Part 8 design for Stage 2 submission

CNWQR

41

CNWQR

38

CNWQR

62

CNWQR

43

Phase 4A – Preparing Part 8 design for Stage 2 submission

Total:

222

Schemes in the Course of Planning Scheme

No.Units Status

Springville House

35

Part 8 approved. To be progressed by Tuath Housing Association. Funding submission made to DHPLG.

Barrack Street Wood Street

32 16

At contract award stage. At contract award stage.

Bramble Cottages Glenamoy Lawn

5 3

Part 8 application to be prepared. Part 8 application to be prepared. Part 8 application to be prepared.

Errigal Heights

32

Foyle Avenue (incl Ardmore Avenue)

3

STAGE 4 submission made to the DHPLG. Refurbishment to be completed. Part 8 application being prepared.

Madonna House - Phase 1 Madonna House- Phase 2 Poulavone, Ballincollig Hawkes Road, Bishopstown

16

6

64 64 49 54 25 43 12 16

Part 8 approved Part 8 advertised Part 8 advertised Part 8 advertised Part 8 advertised Part 8 approved Part 8 approved. Part 8 approved. Part 8 approved. Part 8 approved. Part 8 approved. Part 8 approved. Part 8 approved. Part 8 approved.

Commons Road Old Mallow Road

Sunview

Denroches Cross Coach Street Skehard Road Glen Ryan Road

9

Montenotte

54 11 20

Pouladuff Road

Shanakiel

Spring Lane

8

Watercourse Road

37

16A Kerry Road (Former Sli Gartan), Mayfield

1 7

Part 8 advertised September 2020.

Hollywood Estate

Part 8 advertised July 2020.

Total:

622

Capital Assistance Scheme (Construction) Scheme Respond - St Vincent’s Convent, St. Mary's Road

No. Units

Status

25 25

Pre-planning underway.

Total:

25