CE Management Report October 2020.pdf

CURAHEEN TO CARRIGROHANE FOOTPATH AND CYCLE PATH UPGRADE (600k) Tender process underway for appointment of contractor. Roads Capital Programme: CCC Funded Projects: ST MARY’S CAMPUS works under construction.

HARBOUR VIEW ROAD JUNCTION UPGRADE Contractor appointed and works to commence shortly.

DEANROCK Construction progressing.

Roads Capital Programme: DTTS & CCC Funded Projects: CORK SCIENCE & INNOVATION PARK ROAD PROJECT Land acquisition process is complete. Detailed Design and preparation of construction contract documents for Phase 1A is complete.

Roads Capital Programme: DUCGS & NTA Funded Project: MARY ELMES PEDESTRIAN & CYCLE BRIDGE (€ 5.2 million) The bridge project is compl ete. The repaving of Harley’s Street is complete. Project close out is underway including completion of final snags. Roads Capital Programme: LIHAF Funded Projects: DOCKLANDS TO CITY CENTRE PROJECT (€6.5 million) Detailed design process underway. Revised planning documents are under review. GLANMIRE ROADS IMPROVEMENT SCHEME Compulsory Purchase Order has been submitted to An Bord Pleanala, oral hearing was postponed from 20 th of April due to restrictions surrounding Covid 19. New date is awaited. Section 50 applications for new bridge are awaiting OPW approval and detailed design is continuing. A section 38 for traffic calming Brooklodge Grove is currently out for consultation.

MONAHAN ROAD EXTENSION (€5 millio n) Design Team has been appointed. Preliminary design work is underway. Land Acquisition requirements have been confirmed.

Urban Regeneration & Development Fund: EASTERN GATEWAY BRIDGE The draft appraisal brief & related tender documents as per DPER Public Spending Code requirements are complete. The Appraisal tender documents will be issued to the NTA & LDA for their input prior to publication. Considering options re. the incorporation of bridges and roads into one large planning process. BEAMISH & CRAWFORD QUARTER INFRASTRUCTURE The appraisal process for the selection of the bridges at Proby’s Quay and Crosses Green is progressing as is the detailed design for the public realm enhanc ement of South Main Street, Tuckey Street, Proby’s Quay, Sullivan’s Qu ay, etc.

MARINA PARK PHASE 2. Preparation of design team brief and other related documents is complete.

Bridge Repair and Rehabilitation Projects: DALY’S BRIDGE: Revised arrangements in place for project close out. It is anticipated that bridge will re-open for public use in December.

BANNOW BRIDGE, GRANGE ROAD BRIDGE, BLACKSTONE BRIDGE & HEALY’S BRIDGE: Design Team appointed . RfT advertised for the appointment of a Contractor.

PRINCIPAL INSPECTIONS OF BRIDGE AND CULVERT STRUCTURES WITHIN CORK CITY BOUNDARY 2020: Engineering consultant (WS Atkins) appointed. Inspections 50% complete.

New Cycle Lanes: HORGANS QUAY Construction of the inbound cycle lane is nearing completion.

CENTRE PARK ROAD Construction of the outbound cycle lane is nearing completion.

MONAHAN’S ROAD Construction of the inbound cycle lane is progressing with completion scheduled for the end of November.

SOUTH MALL Construction tender process is underway.

48

Powered by