Regeneration Schemes
No. of Units
Scheme
Status
Phase 2B – Part 8 approved by Council October 2018. Due to be tendered in September 2020. Phase 1C – Part 8 approved by Council October 2018. Due to be tendered in September 2020. Phase 1D – Planning permission in place for Private/AHB delivery of voluntary housing (21 units) – Under construction. Planning application submitted for Affordable Housing to be delivered by AHB (17 units).
CNWQR
38
CNWQR
41
CNWQR
38
Phase 3B – Preparing Part 8 design for Stage 2 submission Phase 4A – Preparing Part 8 design for Stage 2 submission
CNWQR
62
CNWQR
43
Total:
222
Schemes in the Course of Planning
Scheme
No. Of Units
Status
Springville House
35
Part 8 approved. To be progressed by Tuath Housing Association. Funding submission made to DHPLG.
Barrack Street
32
At contract award stage.
Wood Street
16
At contract award stage.
Bramble Cottages
5
Part 8 application to be prepared.
Glenamoy Lawn
3
Part 8 application to be prepared.
Errigal Heights
32
Part 8 application to be prepared.
Foyle Avenue (incl Ardmore Avenue)
3
Stage 4 submission for the DHPLG being prepared
Madonna House - Phase 1
16
Refurbishment to be completed.
Madonna House- Phase 2
6
Part 8 application being prepared.
Poulavone, Ballincollig
70
Part 8 advertised June 2020
Hawkes Road, Bishopstown
67
Part 8 advertised June 2020
20