Infrastructure Projects Roads Capital Programme: TII Funded Project:

N40 SARSFIELD & BANDON ROAD FLYOVER PROJECT (€31.55 million) L ocalised settlement issues on the N40 continue to be monitored. SIAC Ltd has completed significant repairs. The Maintenance Contract for the N40 has now passed to Egis Lagan and TII.

LOWER GLANMIRE ROAD RESURFACING & FOOTPATH REPAIR CONTRACT (€2.5 million) Construction is su bstantially complete with some minor works such as lining, signage and cycle protection measures to be installed in the coming weeks.

WESTERN ROAD RESURFACING AND FOOTPATH REPAIR CONTRACT (€700K) Construction tender documents are under development.

Roads Capital Programme: NTA Funded Projects: CORK CYCLE NETWORK: PHASE 3 – BALLYVOLANE INCLUDING FOX & HOU NDS JUNCTION (€4.0 million) Consultants appointed. Option assessment and data collection underway. SKEHARD ROAD - PHASE 2 PARKHILL TO CHURCH ROAD JUNCTI ON INCLUDING CSO JUNCTION (€3.5 million) Construction contract is complete.

SKEHARD ROAD- PHASE 3 CHURCH ROAD TO BESSBORO JUNCTION (€2 million) appointment of contractor is underway.

DENNEHY’S CROSS TO WILTON GARDENS (€4 million) Preliminary design is c omplete. Part 8 planning proposals were not approved. Discussions are ongoing with the NTA concerning the delivery of the complete corridor project as part of the Cork Bus Connects Project PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 1 (Mahon to Docklands) (€2.5 million) Preliminary Design is complete. Part 8 Planning is approved. Detailed design process is underway. Site investigation contract is complete. Construction tender scheduled to be published in Q4 2020.

PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 2 (Mahon to Passage) ( €4.0 million) Design Team appointment complete.

LEHENAGHMORE ROAD WIDENING & REALIGNMENT PROJECT Preliminary design layout drawings are under development. Land acquisition will be required. Detailed Design Team appointed.

CLARKE’ S HILL Preliminary Design and Part 8 planning is complete. Land Acquisition discussions are underway.

COACH HILL Preliminary layout design is under development.

HORGANS QUAY CYCLE & PEDESTRIAN ENHANCEMENT PROJECT (€0.5 million) Construction tender proc ess is underway. Contractor appointment is complete. Construction scheduled to commence in Q3 2020.

MAHON TO CITY CENTRE TRANSPORT CORRIDOR (€5 million) will be delivered as part of bus connects

EXISTING NORTHERN RING ROAD ENHANCEMENT PROJECT will be delivered as apart of bus connects

CITY CENTRE PUBLIC TRANSPORT IMPROVEMENT SCHEME (€5 million) Construction is complete. Final Account discussions are ongoing.

MCCURTAIN STREET PUBLIC TRANSPORT IMPROVEMENT SCHEME (€8 million) . Part 8 public consultation commenced July 14th.

SOUTH QUAYS PUBLIC TRANSPORT IMPROVEMENT SCHEME (€4.5 mil lion) Consultants appointed. Data collection and option assessment is underway. GRANGE TO TVP PEDESTRIAN & CYCLEWAY Inc. N40 Bridge detailed design is underway. Tender for ground investigation contract issued mid-July.

THOMAS DAVIS BRIDGE JUNCTION IMPROVEMENT SCHEME (€450K) Construction works are complete- signalised junctions now in operation.

SOUTH DOUGLAS ROAD JUNCTION review of previous Part 8 design underway.

BALLYBRACK CYCLE SCHEME Part 8 planning approval in place. brief being prepared for appointment of consultants for detailed design

PEDESTRIAN SAFETY INTERVENTIONS 2019 (€500K) construction completed.