CE Management Report December 2020.pdf

Regeneration Schemes

Scheme

No. of Units

Status

CNWQR 2B

38

Phase 2B – Due to be tendered in March 2021.

CNWQR

41

Phase 1C – Due to be tendered in March 2021.

CNWQR

21

Phase 1D West – The AHB development of 21 units commenced construction in November 2019 and 7 units have been delivered in June 2020. Phase 1D East - Planning application submitted for Affordable Housing to be delivered by O Cualann AHB (17 units). Estimated on site by July 2021.

CNWQR

17

CNWQR

62

Phase 3B – Progress to part 8 by May 2021

CNWQR

43

Phase 4A – Progress to Part 8 by May 2021

CNWQR

24

Phase 2C – under construction. Estimate Substantial Completion June 2021

Total:

246

Capital Assistance Scheme (Construction)

Scheme

No. of units

Status

25

Pre-planning underway.

Respond - St Vincent’s Convent, St. Mary's Road

Total:

25

Capital Works Members will be aware that the Department of Housing, Planning & Local Government (DHLGH) announced delivery targets under the Rebuilding Ireland Action Plan for Housing & Homelessness across a range of housing programmes. Cork City Council successfully met and exceeded its target for 2019, with 697 homes delivered jointly by the Local Authority and AHB Sector under their Build, Acquisition and Leasing delivery programme.

The City Council continues to advance a strong delivery programme which can be summarised as follows:

Construction: Cork City Council placed a contract notice on the E Tenders website and the OJEU (Official Journal of the European Union) to procure innovative solutions to meeting housing targets under the Social Housing Strategy (SHS) including the construction and completion of housing projects under a parallel site acquisition and development agreement with the City Council, using a Competitive Dialogue procurement process. In Phase 1 of Competitive Dialogue, 11 schemes comprising 215 homes have progressed with the approval of the DHLGH. Construction has been completed on 7 schemes at Blackrock, Tramore Road, Ard Aoibhinn, Blarney Street, High Street and White Street totalling 159 homes. A further two schemes consisting of 48 units are due to commence construction in early 2021.