Infrastructure Projects Roads Capital Programme: TII Funded Projects: WESTERN ROAD RESURFACING AND FOOTPATH REPAIR CONTRACT (€1.6m) Construction of footpaths, drainage & carriageways is substantially complete. AIRPORT HILL PAVEMENT RENEWAL CONTRACT (€1.5m) Preliminary design work has commenced for the renewal of pavements & cycle lanes. CORK NORTH RING ROAD Design Team for the route selection process has been appointed. Section 85 Agreement is being prepared. Route selection process will be concluded by the end of 2023. M/N20 CORK LIMEICK MOTORWAY Route selection process is underway. Selection of the preferred route is expected in the coming weeks. Roads Capital Programme: NTA Funded Projects: CORK CYCLE NETWORK: PHASE 3 – BALLYVOLANE INCLUDING FOX & HOUNDS JUNCTION Option assessment and preliminary design ongoing. SKEHARD ROAD- PHASE 3 CHURCH ROAD TO BESSBORO JUNCTION Construction has recommenced following temporarily suspension due to Covid Level 5 restrictions. MCCURTAIN STREET PUBLIC TRANSPORT IMPROVEMENT SCHEME Work ongoing on preparation of tender documents for appointment of contractor. Advance works contract will issue in June. PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 1 (Mahon to Docklands) The construction phase is ongoing. Night operations are proceeding for a period of 5 weeks to facilitate the importation of fill with limited impact on the Marina. PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 2 (Mahon to Passage) (€4.0 million) First round of early consultation is concluded. Preliminary design of the preferred route is underway. LEGHENAGHMORE ROAD WIDENING & REALIGNMENT PROJECT Design Team is appointed. Part 8 planning is approved. The project requires land acquisition (28 distinct plots). Discussions ongoing with Property Dept regarding the appointment of a Valuer. CLARKE’S HILL Design and planning is complete. Land Acquisition discussions are underway. Negotiations are ongoing re. part funding of the project with TII.
COACH HILL Preliminary layout design is under development .
MARINA PROMENADE Procurement of design team is complete. Prelim Design will commence in the coming weeks.
STREETSCAPE RENEWAL OF DOUGLAS ST, MARY ST & WHITE ST Tender documents for the selection of multidisciplinary design team is under development.
RINGMAHON ROAD CYCLE LANES Preliminary Design is underway. Part 8 scheduled for publication during the summer.
KILCULLY & UPPER GLANMIRE PEDESTRIAN IMPROVEMENT SCHEME Preliminary design is complete. Consultation with residents’ groups is ongoing. Design Team procurement is complete. GLANMIRE TO CITY CYCLE NETWORK (Phase 1 Glanmire to Dunkettle) Tender brief and related tender documents are under development for the appointment of the Design Team.
MAHON TO CITY CENTRE TRANSPORT CORRIDOR will be delivered as part of bus connects.
EXISTING NORTHERN RING ROAD ENHANCEMENT PROJECT will be delivered as part of bus connects.
SOUTH QUAYS PUBLIC TRANSPORT IMPROVEMENT SCHEME Option assessment is ongoing.
GRANGE TO TVP PEDESTRIAN & CYCLEWAY inc. N40 Bridge detailed design and preparation of tender documentation is ongoing. Compulsory Acquisition Oder lodged with An Bord Pleanala for required land acquisition. SOUTH DOUGLAS ROAD JUNCTION work ongoing on detailed design and preparation of tender documentation for appointment of contractor is commenced.
BALLYBRACK CYCLE SCHEME Work ongoing on detailed design.
PEDESTRIAN SAFETY INTERVENTIONS 2019 (€500K) construction completed. Project closeout is underway.