CE Management Report May 2020.pdf

Regeneration/Remedial Works Schemes

Scheme

# Units

Status

CNWQR

38

Phase 2B – Part 8 approved by Council October 2018. Due to be tendered in May 2020.

CNWQR

41

Phase 1C – Part 8 approved by Council October 2018. Due to be tendered in May 2020.

CNWQR

38

Phase 1D – Planning permission in place for Private/AHB delivery of voluntary housing (21 units) – Under construction. Planning application submitted for Affordable Housing to be delivered by AHB (17 units).

CNWQR

62

Phase 3B – Preparing Part 8 design for Stage 2 submission

Total:

179

Schemes in the Course of Planning

Scheme

# Units

Status

Springville House

35

Part 8 approved. To be progressed by Tuath Housing Association. Funding submission made to DHPLG.

Barrack Street

32

At contract award stage.

Wood Street

16

At contract award stage.

Bramble Cottages

5

Part 8 application to be prepared.

Glenamoy Lawn

3

Part 8 application to be prepared.

Errigal Heights

20

Stage 2 submitted to DHPLG.

Foyle Avenue (incl Ardmore Avenue)

3

Due to be tendered.

Madonna House - Phase 1

16

Refurbishment to be completed.

Madonna House- Phase 2

6

Part 8 application being prepared.

Poulavone, Ballincollig

70

Part 8 advertised June 2020

Hawkes Road, Bishopstown

67

Part 8 advertised June 2020

Denroches Cross

43

Part 8 advertised June 2020

Coach Street

12

Part 8 approved.

Skehard Road

16

Part 8 approved.

Glen Ryan Road

9

Part 8 approved.

Montenotte

54

Part 8 approved.

Pouladuff Road

11

Part 8 approved.

Spring Lane

8

Part 8 approved.

Watercourse Road

37

Part 8 approved.

Sli Gartan, Mayfield

1

Stage 2 submission being prepared.

Hollywood Estate

7

Part 8 application to be prepared.

Total:

471