Infrastructure Projects __________________________________________________________________________________________________

Roads Capital Programme: TII Funded Projects:

PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 2 (Mahon to Passage) ( €4.0 million) Design Team appointment is complete. LEHENAGHMORE ROAD WIDENING & REALIGNMENT PROJECT Preliminary design layout drawings are under development. Land acquisition will be required.

N40 SARSFIELD & BANDON ROAD FLYOVER PROJECT (€31.55 million) Localised settlement issues on the N40 continue to be monitored. SIAC Ltd has completed significant repairs. The Maintenance Contract for the N40 has now passed to Egis Lagan. LOWER GLANMIRE ROAD RESURFACING & FOOTPATH REPAIR CONTRACT ( €2.5 million) Construction is substantially complete with some minor works such as lining, signage and cycle protection measures to be installed in the coming weeks.

CLARKE’S HILL Preliminary Design and Part 8 planning is complete. Land Acquisition discussions are underway.

COACH HILL Preliminary layout design is under development.

HORGANS QUAY CYCLE & PEDESTRIAN ENHANCEMENT PROJECT (€0.5 million) Construction tender process is underway. Contractor appointment scheduled for coming weeks. MAHON TO CITY CENTRE TRANSPORT CORRIDOR (€5 million) Procurement documents for the appointment of a design team are with NTA for approval to proceed. EXISTING NORTHERN RING ROAD ENHANCEMENT PROJECT Procurement documents for the appointment of a design team with NTA for approval to proceed. CITY CENTRE PUBLIC TRANSPORT IMPROVEMENT SCHEME (€5 million) Construction is complete. Final Account discussions are ongoing. MCCURTAIN STREET PUBLIC TRANSPORT IMPROVEMENT SCHEME (€8 million) Awaiting NTA approval to proceed to Part 8. SOUTH QUAYS PUBLIC TRANSPORT IMPROVEMENT SCHEME (€4.5 million) Consultants appointed. Data collection and option assessment is underway.

Roads Capital Programme: NTA Funded Projects:

CORK CYCLE NETWORK: PHASE 3 – BALLYVOLANE INCLUDING FOX & HOUNDS JUNCTION (€4.0 million) Consultants appointed. Option assessment and data collection underway. SKEHARD ROAD - PHASE 2 PARKHILL TO CHURCH ROAD JUNCTION INCLUDING CSO JUNCTION (€3.5 million) Construction contract is complete. Snagging work is ongoing. SKEHARD ROAD- PHASE 3 CHURCH ROAD TO BESSBORO JUNCTION (€2 million) Tender Assessment stage. DENNEHY’S CROSS TO WILTON GARDENS (€4 million) Preliminary design is complete. Part 8 planning proposals were not approved. Discussions are ongoing with the NTA concerning the delivery of the complete corridor project. PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 1 (Mahon to Docklands) (€2.5 million) Preliminary Design is complete. Detailed design process underway. Site investigation contract underway.