Housing Directorate HOUSING PROGRESS REPORT November 2020 Schemes in Construction
Scheme
No. Units
Status *Estimated completion dates may change due to Covid-19
Estimated Completion Date
Aspen Drive
29
Completed
-
Blarney Street
25
Completed
-
Phase 2A
47
Completed
-
St John’s Well
6
Completed
-
Deanrock
66
Completed
-
White Street
43
Completed
-
High Street
9
Completed
-
Farranferris
86
Tuath – construction underway
Dec-20
Corcoran’s Quay
3
Construction underway.
Dec-21
Millerd Street
25
Completed
Sep-20
Carrs Hill
36
Construction underway.
Sep-20
29 & 30 Lower John Street
17
Construction underway.
Dec-20
Woodfield, Blarney
18
Construction underway.
Jul-20
Phase 2C – CNWQR
24
Construction underway.
Dec-20
Grattan Street -Good Shepherd Cork
33
Construction underway.
Aug-20
Gerald Griffin Street
13
Construction underway.
Dec-20
Ballinure Road
5
Construction underway.
Nov-20
Boherboy Road
153
Construction underway.
Dec-21 w/ interim phasing
St. Joachim and Annes
8
Construction underway – Respond.
Nov-20
166 Sundays Well Road
1
Construction underway - Phase 2/2
Dec-20
Redforge Road
80
Construction underway - Respond.
Dec-21
5/6 Shandon St/9 John Philpott Curran St
9
Construction underway.
Dec-20
Coolroe, Ballincollig
44
Construction underway – Respond.
Dec-20
Gerald Griffin Street/Burkes Avenue
42
Sep-22
Enabling works complete. Main contract at tender stage
Respond – Thomas Davis Street
28
Construction underway.
Dec-21
Boyces Street
51
Construction underway.
Nov-22
Green Lane, Blackpool
112
Enabling Works underway.
Dec-22
Springville House
35
Construction underway.
Jan-22
Cluid - Kerry Pike
22
Construction underway.
Dec-20
Part V and Turnkeys across the city
325
Construction underway.
Various
Total Under Construction:
1395