Regeneration Schemes

Scheme

No. of Units

Status

CNWQR

38

Phase 2B – Part 8 approved by Council November 2018. Due to be tendered in May 2020.

CNWQR

41

Phase 1C – Part 8 approved by Council November 2018. Due to be tendered in May 2020.

CNWQR

38

Phase 1D – Planning permission in place for Private/AHB delivery of voluntary housing (21 units) – Under construction. Planning application submitted for Affordable Housing to be delivered by AHB (17 units).

CNWQR

62

Phase 3B – Preparing Part 8 design for Stage 2 submission

Total:

167

Capital Assistance Scheme (Construction)

Scheme

No. of units

Status

25

Pre-planning underway.

Respond - St Vincent’s Convent, St. Mary's Road

Total:

25

Capital Works Members will be aware that the Department of Housing, Planning & Local Government (DHPLG) announced delivery targets under the Rebuilding Ireland Action Plan for Housing & Homelessness across a range of housing programmes. Cork City Council successfully met and exceeded its target for 2019, with 697 homes delivered jointly by the Local Authority and AHB Sector under their Build, Acquisition and Leasing delivery programme.

The City Council continues to advance a strong delivery programme which can be summarised as follows:

Construction: Cork City Council placed a contract notice on the E Tenders website and the OJEU (Official Journal of the European Union) to procure innovative solutions to meeting housing targets under the Social Housing Strategy (SHS) including the construction and completion of housing projects under a parallel site acquisition and development agreement with the City Council, using a Competitive Dialogue procurement process. In Phase 1 of Competitive Dialogue, 11 schemes comprising 215 homes have progressed with the approval of the DHPLG. Construction has been completed on 7 schemes at Blackrock, Tramore Road, Ard Aoibhinn, Blarney Street , High Street, and White Street totalling 159 homes. A further two schemes consisting of 48 units are due to commence construction in 2020. A further contract notice was placed on the E Tenders website and the OJEU, with a closing date of September 2017, to seek submissions from candidates for the delivery of more new homes using this procurement process. In Phase 2 of Competitive Dialogue, three schemes have commenced on site comprising a total of 35 homes. Further schemes have been shortlisted to progress to the next phase of procurement, involving a Part 8 process, or are at tender stage. Eleven of the schemes under consideration have Part 8 approval in place (360 new homes) and are at tender stage. Two further schemes that are under consideration and going through the Part 8 public consultation process are Sunview and Redemption Heights (89 new homes). Capital appraisals were approved by the DHPLG for the construction of 41 housing units at Gerald Griffin Street & 65 units at Deanrock, Togher. The construction of the units together with a community facility at Deanrock, Togher have reached