CE Management Report November 2020.pdf

Infrastructure Projects Roads Capital Programme: TII Funded Projects:

WESTERN ROAD RESURFACING AND FOOTPATH REPAIR CONTRACT (€700K) Construction of footpaths is well advanced. Resurfacing of carriageways will be undertaken in Dec/Jan 2021. Significant Irish Water works undertaken as part of the project.

Roads Capital Programme: NTA Funded Projects: CORK CYCLE NETWORK: PHASE 3 – BALLYVOLANE INCLUDING FOX & HOUNDS JUNCTION (€4.0 million) Consultants appointed. Preliminary design works underway. SKEHARD ROAD - PHASE 2 PARKHILL TO CHURCH ROAD JUNCTION INCLUDING CSO JUNCTION (€3.5 million) Construction contract is complete. Final Account agreement reached in Nov.

SKEHARD ROAD- PHASE 3 CHURCH ROAD TO BESSBORO JUNCTION (€3 million) Construction has commenced.

PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 1 (Mahon to Docklands) Contractors Ward & Burke have been appointed. Construction mobilization to commence in Dec with major works expected from January onwards. PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 2 (Mahon to Passage) (€4.0 million) Design Team appointment complete. Preliminary design is underway. LEGHENAGHMORE ROAD WIDENING & REALIGNMENT PROJECT Design Team is appointed. Part 8 planning process is underway. The project requires extensive land acquisition (28 distinct plots). CLARKE’S HILL Design and Part 8 planning is complete. Land Acquisition discussions are underway. Negotiations with TII are ongoing Re. the part funding of the project.

COACH HILL Preliminary layout design is under development .

MAHON TO CITY CENTRE TRANSPORT CORRIDOR will be delivered as part of bus connects.

EXISTING NORTHERN RING ROAD ENHANCEMENT PROJECT will be delivered as a part of bus connects.

CITY CENTRE PUBLIC TRANSPORT IMPROVEMENT SCHEME Construction is complete. Final has been agreed.

MCCURTAIN STREET PUBLIC TRANSPORT IMPROVEMENT SCHEME Part 8 was approved by Council on the 12 th of October 2020; work ongoing on detailed design. SOUTH QUAYS PUBLIC TRANSPORT IMPROVEMENT SCHEME Consultants appointed. Data collection and option assessment is ongoing. GRANGE TO TVP PEDESTRIAN & CYCLEWAY inc. N40 Bridge detailed design is underway. Ground Investigation contract is now completed.

SOUTH DOUGLAS ROAD JUNCTION Submissions being assessed and report will be brought to Council for approval shortly.

BALLYBRACK CYCLE SCHEME Part 8 planning approval in place. Consultant appointed for detailed design.

PEDESTRIAN SAFETY INTERVENTIONS 2019 (€500K) construction completed.

PEDESTRIAN SAFETY INTERVENTIONS 2020 (€500K) Contractor has been appointed for Vicar’s Road, Dublin Hill, Ringmahon Road and Rathmore Road. Detailed design underway for St. Patrick’s Roa d. NORTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT. Design Team appointed for the route selection assessment. Discussions ongoing with adjoining developers/land owners Re SHD’s and requirements for set aside lands. SOUTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT Tender process for procurement of the route selection design team is underway. Design Team appointment scheduled for Q4 2020. CURAHEEN TO CARRIGROHANE FOOTPATH AND CYCLE PATH UPGRADE (600k) Contractor has been appointed works will commence in early January. Roads Capital Programme: DTTS & CCC Funded Projects: CORK SCIENCE & INNOVATION PARK ROAD PROJECT Land acquisition process is complete. Detailed Design and preparation of construction contract documents for Phase 1A is complete.

Powered by