CE Management Report February 2021.pdf

Infrastructure Projects Roads Capital Programme: TII Funded Projects: WESTERN ROAD RESURFACING AND FOOTPATH REPAIR CONTRACT (€1.6m) Construction of footpaths and carriageways is ongoing. All surface drainage work is now complete. AIRPORT HILL PAVEMENT RENEWAL CONTRACT (€1.5m) Preliminary design work has commenced for the r enewal of pavements. CORK NORTH RING ROAD Design Team for the route selection process has been appointed. Section 85 Agreement is being prepared. Route selection process will be concluded by the end of 2022. Roads Capital Programme: NTA Funded Projects: CORK CYCLE NETWORK: PHASE 3 – BALLYVOLANE INCLUDING FOX & HOUNDS JUNCTION Option assessment and preliminary design ongoing. SKEHARD ROAD- PHASE 3 CHURCH ROAD TO BESSBORO JUNCTION Construction has been temporarily suspended due to Covid Level 5 restrictions. PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 1 (Mahon to Docklands) Contractors Ward & Burke have been appointed. Site clearance work is underway. PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 2 (Mahon to Passage) (€4.0 million) Design Team appointment complete. Preliminary design is underway. Preliminary consultation Re. route options is ongoing. LEGHENAGHMORE ROAD WIDENING & REALIGNMENT PROJECT Design Team is appointed. Part 8 planning is approved. The project requires land acquisition (28 distinct plots). Procurement of design team for detailed design to project completion is underway. CLARKE’S HILL Design and planning is complete. Land Acquisition discussions are underway. Negotiations with TII and NTA are ongoing Re. the part funding of the project. COACH HILL Preliminary layout design is under development . MARINA PROMENADE. Procurement of design team is ongoing. STREETSCAPE RENEWAL OF DOUGLAS ST, MARY ST & WHITE ST Tender documents for the selection of multidisciplinary design team is under development. Procurement/design completion will be published in April. RINGMAHON ROAD CYCLE LANES Design Team will be appointed for Preliminary Design in early March. KILCULLY & UPPER GLANMIRE PEDESTRIAN IMPROVEMENT SCHEME Preliminary design is co mplete. Consultation with residents’ groups is ongoing. Phase 1 works will be delivered this year with Phase 2 to follow next year subject to the acquisition of lands. GLANMIRE TO CITY CYCLE NETWORK (Phase 1 Glanmire to Dunkettle) Tender brief and related tender documents are under development for the appointment of the Design Team. MAHON TO CITY CENTRE TRANSPORT CORRIDOR will be delivered as part of bus connects.

EXISTING NORTHERN RING ROAD ENHANCEMENT PROJECT will be delivered as part of bus connects.

MCCURTAIN STREET PUBLIC TRANSPORT IMPROVEMENT SCHEME Work ongoing on detailed design.

SOUTH QUAYS PUBLIC TRANSPORT IMPROVEMENT SCHEME Option assessment is ongoing.

GRANGE TO TVP PEDESTRIAN & CYCLEWAY inc. N40 Bridge detailed design and land acquisition discussions are underway. SOUTH DOUGLAS ROAD JUNCTION work commenced on detailed design.

BALLYBRACK CYCLE SCHEME work ongoing on detailed design. PEDESTRIAN SAFETY INTERVENTIONS 2019 (€500K) construction completed.

PEDESTRIAN SAFETY INTERVENTIONS 2020/ 2021 Construction has been temporarily suspended due to Covid Level 5 restrictions.at Vicar’s Road once complete construction will follow for onto Dublin Hill, Ringmahon Road and Rathmore Road. Detailed design underway for St. Patrick’s Road. Section 38 has been advertised for Alderbrook in Frankfield. Prelim design underway at Popham’s Road NORTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT Design Team appointed for the route selection assessment. Discussions ongoing with adjoining devel opers/landowners Re SHD’s and requirements for set aside lands.

SOUTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT Data collection and route selection assessment ongoing.