Housing Directorate Housing Progress Report March 2021
Schemes in Construction
Scheduled Completion Date
Status *Estimated completion dates may change due to Covid-19
Scheme
No Units
Aspen Drive
29
Completed
-
Blarney Street
25
Completed
-
Phase 2A
47
Completed
-
St John’s Well
6
Completed
-
Deanrock
66
Completed
-
White Street
43
Completed
-
High Street
9
Completed
-
Farranferris
86
Tuath – construction underway
Dec-20
Corcoran’s Quay
3
Construction underway.
Dec-21
Millerd Street
25
Completed
Sep-20
Carrs Hill
36
Construction underway.
Sep-20
29 & 30 Lower John Street
17
Completed
Mar-21
Woodfield, Blarney
18
Completed
Dec-20
Phase 2C – CNWQR
24
Construction underway.
Dec-20
Grattan Street -Good Shepherd Cork
33
Completed
Dec-20
Gerald Griffin Street
13
Construction completing
Mar-21
Ballinure Road
5
Construction completing
Mar-21
Dec-21 with interim phasing
Boherboy Road
153
Construction underway.
St. Joachim and Annes
8
Completed
Nov-20
166 Sundays Well Road
1
Completed
Dec-20
Construction underway - Respond. Phased Delivery.
Redforge Road
80
Dec-21
5/6 Shandon St/9 John Philpott Curran St
9
Construction Completing.
Mar-21
Coolroe, Ballincollig
44
Completed
Dec-20
Enabling works complete. Main contract at tender stage
Gerald Griffin Street/Burkes Avenue
42
Sep-22
Respond – Thomas Davis Street
28
Construction underway.
Dec-21
Boyces Street
51
Construction underway.
Nov-22
Green Lane, Blackpool
112
Enabling Works underway.
Dec-22
Springville House
35
Tuath – construction underway
Jan-22
Kerry Pike
22
Cluid – phase 1 complete (12 units)
Mar-21
Part V and Turnkeys across the city
232
Construction underway.
Various
Coach Street
12
Contract awarded.
Mar-22
Spring Lane
8
Construction underway.
May-22
Shanakiel
20
Contract awarded.
May-22
Watercourse Road
37
Construction underway.
Mar-22
Montenotte
27
Contract awarded.
Oct-22
Total:
1406
19