CE Management Report March 2021.pdf

Capital Assistance Scheme (Construction)

Scheme

No. of units Status

Respond - St Vincent’s Convent, St. Mary's Road

25

Pre-planning underway.

Total:

25

Regeneration Schemes

Scheme

No. of Units Status

CNWQR 2B

38

Phase 2B – Due to be tendered in April 2021.

CNWQR

41

Phase 1C – Due to be tendered in April 2021.

CNWQR

21

Phase 1D West – The AHB development of 21 units commenced construction in November 2019 with 7 units delivered in June 2020. Remaining units due for completion Q2 2021 Phase 1D East - Planning application submitted for Affordable Housing to be delivered by O Cualann AHB (17 units). Estimated on site by July 2021.

CNWQR

17

CNWQR

62

Phase 3B – Progress to part 8 by May 2021

CNWQR

43

Phase 4A – Progress to Part 8 by May 2021

CNWQR

24

Phase 2C – under construction.

Total:

246

Schemes in the Course of Planning

Scheme

No. Of Units Status

Springville House

35

Part 8 approved. To be progressed by Tuath Housing Association. Funding submission made to DHPLG.

Barrack Street

32

At contract award stage.

Wood Street

16

At contract award stage.

Bramble Cottages

5

Part 8 application advertised January 2021.

Glenamoy Lawn

3

Part 8 approved.

Errigal Heights

34

Part 8 application to be prepared.

Foyle Avenue (incl Ardmore Avenue)

3

STAGE 4 submission made to the DHPLG.

Madonna House - Phase 1

16

Refurbishment to be completed.

Madonna House- Phase 2

6

Part 8 application being prepared.

Poulavone, Ballincollig

64

Part 8 approved.

20