PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 1 (Mahon to Docklands) Contractors Ward & Burke have been appointed. Site clearance work is underway. Substantive works scheduled to commence in early April
PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 2 (Mahon to Passage) (€4.0 million) Design Team appointment complete. Preliminary design is underway. Preliminary consultation Re. route options undertaken.
LEGHENAGHMORE ROAD WIDENING & REALIGNMENT PROJECT Design Team is appointed. Part 8 planning is approved. The project requires land acquisition (28 distinct plots). Procurement of design team for detailed design to project completion is underway.
CLARKE’S HILL Design and planning is complete. Land Acquisition discussions are underway. Negotiations are ongoing Re. the part funding of the project.
COACH HILL Preliminary layout design is under development .
MARINA PROMENADE. Procurement of design team is ongoing.
STREETSCAPE RENEWAL OF DOUGLAS ST, MARY ST & WHITE ST Tender documents for the selection of multidisciplinary design team is under development. Procurement/design completion will be published in April.
RINGMAHON ROAD CYCLE LANES Design Preliminary Design is underway.
KILCULLY & UPPER GLANMIRE PEDESTRIAN IMPROVEMENT SCHEME Preliminary design is complete. Consultation with residents’ groups is ongoing. Phase 1 works will be delivered this year with Phase 2 to follow next year subject to the acquisition of lands.
GLANMIRE TO CITY CYCLE NETWORK (Phase 1 Glanmire to Dunkettle) Tender brief and related tender documents are under development for the appointment of the Design Team.
MAHON TO CITY CENTRE TRANSPORT CORRIDOR will be delivered as part of bus connects.
EXISTING NORTHERN RING ROAD ENHANCEMENT PROJECT will be delivered as part of bus connects.
MCCURTAIN STREET PUBLIC TRANSPORT IMPROVEMENT SCHEME Work ongoing on preparation of tender documents for appointment of contractor
SOUTH QUAYS PUBLIC TRANSPORT IMPROVEMENT SCHEME Option assessment is ongoing.
GRANGE TO TVP PEDESTRIAN & CYCLEWAY inc. N40 Bridge detailed design and land acquisition discussions are underway.
SOUTH DOUGLAS ROAD JUNCTION work ongoing on detailed design.
BALLYBRACK CYCLE SCHEME work ongoing on detailed design.
PEDESTRIAN SAFETY INTERVENTIONS 2019 (€500K) construction completed. Project closeout is underway.
PEDESTRIAN SAFETY INTERVENTIONS 2020/ 2021 Construction completed at Vicar’s Road and is now ongoing on Ringmahon road once complete construction will follow for onto Dublin Hill and Rathmore Road. Detailed design underway for St. Patrick’s Road. Section 38 will go to council for Approval in April for Alderbrook in Frankfield. Prelim design underway at Popham’s Road
NORTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT Design Team appointed for the route selection assessment. Discussions ongoing with adjoining developers/landowners Re SHD’s and requirements for set aside lands.
SOUTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT Data collection and route selection assessment ongoing.
CURAHEEN TO CARRIGROHANE FOOTPATH AND CYCLE PATH UPGRADE Construction has recommenced on Carrigrohane to Model farm Road section.
40
Powered by FlippingBook