CE Management Report February 2020.pdf

Carrs Hill

36

0

36

Construction underway.

May-20

Castletreasure

2

0

2

Construction underway.

Nov-19

Togher Cross, Lehenaghmore

9

9

0

Construction complete – Clúid Housing Association.

Nov-19

Maryborough Ridge

52

52

0

Tuath Housing Association.

Dec-19

Ballinure Road

5

0

5

Construction underway.

Sept-20

Boyces Street

51

0

51

Construction underway.

Nov-22

Ballinlough Road

6

6

0

Construction completed.

Nov-19

Gearneys Boreen

3

3

0

Practical completion.

Dec-19

Lower Glanmire Road

8

8

0

Galtan CLG.

Dec-19

Boherboy Road

153

0

153

Construction underway.

Sept-20 (Phase 1)

Blackrock Villas

5

5

0

Construction completed.

Dec-19

The Ferns, Ballincollig

4

4

0

Construction completed.

Dec-19

Respond – Thomas Davis Street

28

0

28

Construction underway.

Apr-21

Part V and Turnkeys across the city

141

0

141

Construction underway.

Various

Total:

1365

632

733

Regeneration/Remedial Works Schemes

Scheme

No. of Units Status

Phase 2B – Part 8 approved by Council October 2018. Due to be tendered in March 2020.

CNWQR

38

Phase 1C – Part 8 approved by Council October 2018. Due to be tendered in March 2020.

CNWQR

41

CNWQR

38

Phase 1D – Planning permission in place for Private/AHB delivery of voluntary housing (21 units) – Under construction. Planning application submitted for Affordable Housing to be delivered by AHB (17 units).

CNWQR

62

Phase 3B – Preparing Part 8 design for Stage 2 submission

Total:

179

Page | 19