CE Management Report September 2020.pdf

Tuath: Springville House

35

Construction underway

Jan-22

2 phases: Oct 20 – Feb 21

Tuath: Croppy Boy

21

Construction underway

Part V and Turnkeys across the city

132

Construction underway.

Various

Total:

1220

Regeneration Schemes

Scheme

No. of Units

Status

CNWQR

38

Phase 2B – Part 8 approved by Council October 2018. Due to be tendered in November 2020.

CNWQR

41

Phase 1C – Part 8 approved by Council October 2018. Due to be tendered in November 2020.

CNWQR

38

Phase 1D – Planning permission in place for Private/AHB delivery of voluntary housing (21 units) – Under construction. Planning application approved for Affordable Housing to be delivered by AHB (17 units).

CNWQR

62

Phase 3B – Preparing Part 8 design for Stage 2 submission

CNWQR

43

Phase 4A – Preparing Part 8 design for Stage 2 submission

Total:

222

Schemes in the Course of Planning

Scheme

No. Of Units

Status

Barrack Street

32

At contract award stage.

Wood Street

16

At contract award stage.

Bramble Cottages

5

Part 8 application being prepared.

Glenamoy Lawn

3

Part 8 advertised September 2020

Errigal Heights

20

Part 8 application being prepared.

3

At contract award stage.

Foyle Avenue (incl Ardmore Avenue)

Madonna House - Phase 1

16

Refurbishment to be completed.

Madonna House- Phase 2

6

Part 8 application being prepared.

Poulavone, Ballincollig

70

Part 8 approved

Hawkes Road, Bishopstown

67

Part 8 in progress

Denroches Cross

43

Part 8 approved

Sunview, South Douglas Road

25

Part 8 in progress

57

Part 8 in progress

Old Mallow Road (former Bolands site)

23