Litter Fines
140
120
100
80
60
40
20
0
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Court Prosecutions
Issued
Paid
Prosecutions Lost
Prosecutions Taken
Prosecutions Won
Infrastructure Projects Roads Capital Programme: TII Funded Projects:
N40 SARSFIELD & BANDON ROAD FLYOVER PROJECT (€31.55 millio n) Localised settlement issues on the N40 continue to be monitored. SIAC Ltd has completed significant repairs. The Maintenance Contract for the N40 has now passed to Egis Lagan and TII. LOWER GLANMIRE ROAD RESURFACING & FOOTPATH REPAIR CONTRACT (€2.5 mi llion) Construction is substantially complete with some minor works such as lining, signage and cycle protection measures to be installed in the coming weeks.
WESTERN ROAD RESURFACING AND FOOTPATH REPAIR CONTRACT (€700K) Construction is underway.
Roads Capital Programme: NTA Funded Projects: CORK CYCLE NETWORK: PHASE 3 – BALLYVOLANE INCLUDING FOX & HOUNDS JUNCTION (€4.0 million) Consultants appointed. Preliminary design works underway SKEHARD ROAD - PHASE 2 PARKHILL TO CHURCH ROAD JUNCTION INCLUDING CSO JUN CTION (€3.5 million) Construction contract is complete. SKEHARD ROAD- PHASE 3 CHURCH ROAD TO BESSBORO JUNCTION (€2 million) appointment of contractor is underway. DENNEHY’S CROSS TO W ILTON GARDENS (€4 million) Preliminary design is complete. Part 8 planning proposals were not approved. Discussions are ongoing with the NTA concerning the delivery of the complete corridor project as part of the Cork Bus Connects Project PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 1 (Mahon to Docklands) (€2.5 million) P art 8 Planning is approved. Detailed design process is complete. Site investigation contract is complete. Construction tender process is underway. PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 2 (Mahon to Passage) (€4.0 million) Design Team appointment complete. Preliminary design is underway. LEHENAGHMORE ROAD WIDENING & REALIGNMENT PROJECT. Design Team is appointed. Part 8 planning drawings are under development. Extent of proposed land acquisition is being determined.
CLARKE’S HILL Preliminary Design and Part 8 planning is complete. Land Acquisition discussions are underway.
44
Powered by FlippingBook