COACH HILL Preliminary layout design is under development.
MAHON TO CITY CENTRE TRANSPORT CORRIDOR (€5 million) will be delivered as part of bus connects
EXISTING NORTHERN RING ROAD ENHANCEMENT PROJECT will be delivered as apart of bus connects
CITY CENTRE PUBLIC TRANSPORT IMPROVEMENT SCHEME (€5 million) Construction is complete. Final Account discussions are ongoing. MCCURTAIN STREET PUBLIC TRANSPORT IMPROVEMENT SCHEME (€8 millio n). Part 8 public consultation has been completed. Submissions now being assessed and draft report for council being prepared. SOUTH QUAYS PUBLIC TRANSPORT IMPROVEMENT SCHEME (€4.5 million) Consultants appointed. Data collection and option assessment is ongoing. GRANGE TO TVP PEDESTRIAN & CYCLEWAY inc. N40 Bridge detailed design is underway. Contractor for ground investigation contract appointed, works due to commence shortly. THOMAS DAVIS BRIDGE JUNCTION IMPROVEMENT SCHEME (€450K) Construction works are complete- signalised junctions now in operation. SOUTH DOUGLAS ROAD JUNCTION draft Part 8 design documents currently being finalised with NTA for approval prior to going to public consultation beginning of October.
BALLYBRACK CYCLE SCHEME Part 8 planning approval in place. Tenders being assessed for appointment of consultant for detailed design.
PEDESTRIAN SAFETY INTERVENTIONS 2019 (€500K) construction completed.
PEDESTRIAN SAFETY INTERVENTIONS 2020 (€500K) Section 38’s were approved by council for new schemes at Vicar’s Road, Dublin Hill, Ringmahon Road and Rathmore Road. Detailed design is being finalised and will go to tender in October. A further scheme at St Patrick’s road will go out to section 38 in October NORTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT Tender process for procurement of the route selection design team is underway. Design Team appointment scheduled for Q4 2020. SOUTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT Tender process for procurement of the route selection design team is underway. Design Team appointment scheduled for Q4 2020. CURAHEEN TO CARRIGROHANE FOOTPATH AND CYCLE PATH UPGRADE (600k) Tender documentation being prepared . Scheme to go to tender in October. Roads Capital Programme: CCC Funded Projects: ST MARY’S CAMPUS works under construction.
HARBOUR VIEW ROAD JUNCTION UPGRADE appointment of contractor is underway and works to commence shortly.
DEANROCK Tender assessment underway. Construction scheduled to commence in Q4.
Roads Capital Programme: DTTS & CCC Funded Projects: CORK SCIENCE & INNOVATION PARK ROAD PROJECT Land acquisition process is complete. Detailed Design and preparation of construction contract documents for Phase 1A is complete.
Roads Capital Programme: DUCGS & NTA Funded Project: MARY ELMES PEDESTRIAN & CYCLE BRIDGE (€5.2 million) The bridge project is complete. The repaving of Harley’s Street is complete.
45
Powered by FlippingBook