CE Management Report January 2020.pdf

Árus Mhuire, Skehard Road

30

30

0

Construction completed.

Dec-18

Tramore Road

4

4

0

Construction completed.

Dec-18

Churchfield Place East

3

3

0

Construction completed.

Dec-18

Ard Aoibhinn, Mayfield Phase 2

5

5

0

Construction completed.

Dec-18

Construction completed - Respond.

North Abbey Street

6

6

0

Dec-18

Deanrock Mews

4

4

0

Construction completed.

Dec-18

Construction completed - Galtan CLG.

2 Braemar

3

3

0

Dec-18

Corcoran’s Quay

3

0

3

Construction underway.

Apr-20

Farranferris Crescent

5

5

0

Practical completion

Dec-19

High Street

9

9

0

Practical completion

Dec-19

Deanrock

66

66

0

Practical completion

Dec-19

Blarney Street

25

25

0

Practical completion

Dec-19

Phase 2A - CNWQR

47

47

0

Practical completion

Dec-19

White Street

43

43

0

Practical completion

Dec-19

Construction underway - Respond

Millerd Street

25

0

25

Apr-20

Construction underway - Respond.

Redforge Road

80

0

80

Dec-20

Gerald Griffin Street/Burkes Avenue

42

0

42

Enabling Works completed. Tenders to be invited for main contract.

May-21

66- 68 St. John’s Well

6

6

0

Practical completion

Dec-19

Phase 2C – CNWQR

24

0

24

Construction underway.

Aug-20

29 & 30 Lower John Street

17

0

17

Construction underway.

Jul-20

Gerald Griffin Street

13

0

13

Construction underway.

Sep-20

Grattan Street -Good Shepherd Cork

33

0

33

Construction underway.

Aug-20

Leeside Apartments

78

78

0

Construction completed.

Mar-19

5/6 Shandon St/9 John Philpott Curran St

9

0

9

Construction underway.

Dec-20

St. Joachim and Annes

8

0

8

Construction underway – Respond.

Nov 20

Coolroe, Ballincollig

44

0

44

Construction underway – Respond.

Dec-20

Woodfield, Blarney

18

0

18

Construction underway.

Jul-20

Page | 17