Housing Directorate Housing Progress Report March 2020
Schemes in Construction:
Scheme
No. of Units
Completed to date
Balance Status
Estimated Completion
The Meadows Phase 2
21
21
0
Practical completion
Dec-19
The Meadows Phase 3
17
17
0
Practical completion
Dec-19
Corcoran’s Quay
3
0
3
Construction underway.
Apr-20
Farranferris Crescent
5
5
0
Practical completion
Dec-19
High Street
9
9
0
Practical completion
Dec-19
Deanrock
66
66
0
Practical completion
Dec-19
Blarney Street
25
25
0
Practical completion
Dec-19
Phase 2A - CNWQR
47
47
0
Practical completion
Dec-19
White Street
43
43
0
Practical completion
Dec-19
Millerd Street
25
0
25
Construction underway - Respond. Construction underway - Respond. Enabling Works completed. Tenders to be invited for main contract.
Apr-20
Redforge Road
80
0
80
Dec-20
Gerald Griffin Street/Burkes Avenue
42
0
42
May-21
66- 68 St. John’s Well
6
6
0
Practical completion
Dec-19
Phase 2C – CNWQR
24
0
24
Construction underway.
Aug-20
29 & 30 Lower John Street
17
0
17
Construction underway.
Jul-20
Gerald Griffin Street
13
0
13
Construction underway.
Sep-20
Grattan Street -Good Shepherd Cork
33
0
33
Construction underway.
Aug-20
Leeside Apartments
78
78
0
Construction completed.
Mar-19
5/6 Shandon St/9 John Philpott Curran St
9
0
9
Construction underway.
Dec-20
St. Joachim and Annes
8
0
8
Construction underway – Respond. Construction underway – Respond.
Nov 20
Coolroe, Ballincollig
44
0
44
Dec-20
16