SOUTH DOUGLAS ROAD JUNCTION Part 8 process not completed.
BALLYBRACK CYCLE SCHEME Part 8 planning approval in place.
PEDESTRIAN SAFETY INTERVENTIONS (€500K) construction works are completed at Mick Barry Rd & Our Lady Crowned junction and works are ongoing at 4 remaining locations.
Section 38’s are out for public consultation for a new scheme at Vicar’s Road, Dublin Hill and Ringmahon Road. Submissions o n these proposals are due on 9 th of April.
NORTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT The preparation of contract documents for the appointment of a design team to determine the route of the proposed northern distributer road is progressing. SOUTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT The preparation of contract documents for the appointment of a design team to determine the route of the proposed southern distributer road is progressing.
Roads Capital Programme: CCC Funded Projects:
ST MARY’S CAMPUS (€150k) Preparation of tender documentation is underway.
HARBOUR VIEW ROAD JUNCTION UPGRADE (€650K) ; Land acquisition and detailed design are underway.
DEANROCK (€250k) The preferred layout has been selected. Costing and discussions are underway with the NTA regarding funding for the project.
Roads Capital Programme: DTTS & CCC Funded Projects:
2019 ROAD RESURFACING CONTRACT 2019 Road Resurfacing Programme is complete.
CORK SCIENCE & INNOVATION PARK ROAD PROJECT Land acquisition process is progressing. Detailed Design and preparation of construction contract documents for Phase 1A is progressing.
Roads Capital Programme: DUCGS & NTA Funded Project:
MARY ELMES PEDESTRIAN & CYCLE BRIDGE (€5.2 million) The bridge project is complete. The repaving of Harley’s Street is substantially complete. The remaining work is scheduled to be undertaken in the coming weeks.
Roads Capital Programme: LIHAF Funded Projects: DOCKLANDS to CITY CENTRE PROJECT (€6.5 million) The preliminary design is complete. Traffic counts, building surveys and site investigation contracts are complete. New Part 8 Planning process to be undertaken. Detailed Design and preparation of construction contract documents is progressing. GLANMIRE ROADS IMPROVEMENT SCHEME Compulsory Purchase Order has been submitted to An Bord Pleanala, we are awaiting confirmation of a date for oral hearing. Section 50 applications for new bridge are awaiting OPW approval and detailed design is continuing.
MONAHAN ROAD EXTENSION (€5 million) Tender Documents for the selection of the design team are progressing.
Urban Regeneration & Development Fund:
EASTERN GATEWAY BRIDGE The draft appraisal brief & related tender documents as per DPER Public Spending Code requirements are complete. The Appraisal tender documents will be issued to LDA for their input prior to publication.
BEAMISH & CRAWFORD QUARTER INFRASTRUCTURE The tender process for selection of the design team is nearing completion.