Park Projects
Marina Park:
Phase 1 works ongoing with an estimated completion date of October 2021.
Tramore Valley Park:
Half Moon Lane Upgrade to allow pedestrian/cycle access to TVP. Contractor on site and works progressing – scheduled completion late October.
Clashduv Park:
New canal crossing at the allotment’s car park. Regrading and drainage work to soccer pitch are completed
Ballincollig Regional Park:
Automatic Toilet scheduled to be installed in late October.
Fionn Laoi:
Outstanding works by Developer near completion.
Water Fountains
Site investigations underway in preparation for installation at Tramore Valley Park, Fitzgerald’s Park, Ballincollig Regional Park, Bishopstown Park and Gerry O’ Sullivan Park.
Wheelchair Swings
5 Wheelchair Swings to be installed at Meelick Park, Gerry O’ Sullivan Park, Pophams Park, Clashduv Park and Lough Mahon Park during November/December.
Mahon Golf Course Car Park
Preparation of tender documents for resurfacing and lining underway
Park Events
We have seen some small events and exercise groups take place in the parks such as Circus Training, Yoga, and various exercise classes since the easing of COVID restrictions.
Various contacts with Tidy Towns Groups, Renewal Groups, Residents Associations, Community Associations etc. Progressed new Garden Project Tory Top Park with Ballyphehane/Togher CDP.
Dog Control: Dog Wardens patrolling Parks and Walkways
Tree Works Location
Tree Species
Quantity
Type of work carried out
Reason work was carried out
Date Work was carried Out
South Mall Kenley Drive Douglas Road Wilton Court Laburnum Park
Lime
2
Planned remedial prunning Planned remedial prunning
H&S concerns H&S concerns H&S concerns
05/09/21
Sycamore Variety
06-09-21 to 10-09-21
Alder
4 3 1 2
Fell and remove Fell and remove
14/09/21 24/09/21 27/09/21 30/09/21
Elm
Dead
Birch Lime
Planned remedial prunning Planned remedial prunning
H&S concerns H&S concerns
Gate Lodge
47