CE Management Report October 2021

Infrastructure Projects Roads Capital Programme: TII Funded Projects WESTERN ROAD RESURFACING AND FOOTPATH REPAIR CONTRACT (€1.6m) Construction of footpaths, drainage & carriageways are complete. Work on remaining asphalt and snagging is ongoing.

AIRPORT HILL PAVEMENT RENEWAL CONTRACT (€1.5m) Contractor appointed. Work exp ected to commence in the coming weeks. A six-week work programme.

CORK CITY NORTHERN TRANSPORT PROJECT (formerly Cork North Ring Road) Design Team for the route selection process has been appointed. Section 85 Agreement is being prepared. Route selection process will be concluded by the end of 2023. Project website, logo, name have been agreed with TII & Project Team. Strategic Assessment Report (SAR) submitted to Department of Transport prior to it being issued to DPER.

M/N20 CORK LIMEICK MOTORWAY Route selection process is underway. Selection of the preferred route is expected in the New Year. Project Phasing being considered.

N40 SARSFIELD & BANDON RD FLYOVER PROJECT Settlement of the pavement continues to be monitored. The Contractor has undertaken several repairs and has agreed to complete other repairs to the pavement where cracking & settlement has occurred.

Roads Capital Programme: NTA Funded Projects CORK CYCLE NETWORK: PHASE 3 – BALLYVOLANE INCLUDING FOX & HOUNDS JUNCTION Preparation of Part 8 documentation is underway.

SKEHARD ROAD- PHASE 3 CHURCH ROAD TO BESSBORO JUNCTION Construction ongoing.

MCCURTAIN STREET PUBLIC TRANSPORT IMPROVEMENT SCHEME Procurement of the contractor for main works is underway. Advance works contract is nearing completion. PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 1 (Mahon to Docklands) C onstruction ongoing. Phase 1 (The Marina to Blackrock Station) has reopened. Phase 4 (N40 to Mahon) has reopened. The contractor is now working on Phase 2 (Blackrock Station to Skehard Rd). The new pedestrian/cycle bridge will be lifted into place in December. PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 2 (Mahon to Passage) (€4.0 million) First round of early consulta tion is concluded. Design of the preferred route is complete. Planning to commence before the end of the year. LEGHENAGHMORE ROAD WIDENING & REALIGNMENT PROJECT Design Team is appointed. Part 8 planning is approved. The project requires land acquisition (28 distinct plots). Land acquisition negotiations ongoing via Valuation Team. CLARKE’S HILL Design and planning is complete. Land Acquisition discussions are underway. Negotiations are ongoing re. part funding of the project with TII.

COACH HILL Preliminary layout design is under development .

MARINA PROMENADE D esign Team have been appointed. Prelim Design optioneering is progressing.

STREETSCAPE RENEWAL OF DOUGLAS ST, MARY ST & WHITE ST Tender documents for the selection of multidisciplinary design team is under development. MAHON CYCLE ROUTE Preliminary Design is complete. Part 8 documents under development. Planning to be published before the end of the year.

KILCULLY & UPPER GLANMIRE PEDESTRIAN IMPROVEMENT SCHEME Preliminary design is complete. Consultation with residents’ groups is ongoing. Design Consultants have been appointed.

GLANMIRE TO CITY CYCLE NETWORK (Phase 1 Glanmire to Dunkettle) Design Team appointed. Prelim Design is underway.

MAHON TO CITY CENTRE TRANSPORT CORRIDOR will be delivered as part of bus connects.

EXISTING NORTHERN RING ROAD ENHANCEMENT PROJECT will be delivered as part of bus connects.

SOUTH QUAYS PUBLIC TRANSPORT IMPROVEMENT SCHEME Option assessment is ongoing.

GRANGE TO TVP PEDESTRIAN & CYCLEWAY inc. N40 Bridge Procurement of contractor is underway. Land acquisition is ongoing.

SOUTH DOUGLAS ROAD JUNCTION Procurement of contractor is underway.