CE Management Report October 2021

BALLYBRACK CYCLE SCHEME Work ongoing on detailed design. Ground investigation underway.

PEDESTRIAN SAFETY INTERVENTIONS 2019 (€500K) Construction completed. Project closeout is underway.

PEDESTRIAN SAFETY INTERVENTIONS 2020/ 2021 Final snagging is being completed on Rathmore Road, Ringmahon Road, Vicar’ s Road and Dublin Hill. Construction commenced as one contract for St. Patrick’s Road, Alderbrook in Frankfield and Popham’s Ro ad as one contract. VIADUCT TO CITY CENTRE PHASE 1 (Viaduct to Kinsale Road) Design Team have been appointed. Prelim Design optioneering is progressing. NORTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT Route Options sifting is advancing. Discussions ongoing with adjoining developers/landowners re. SHD’s and requirements for set aside lands. The Strategic Assessment Report (SAR has b een submitted to the NTA, after which it will go to the Department of Transport and DPER.

SOUTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT Route option identification is ongoing.

CURAHEEN TO CARRIGROHANE FOOTPATH AND CYCLE PATH UPGRADE C onstruction is being completed.

CURRAGH RD/ PEARSE ROAD JUNCTION UPGRADE SCHEME Work ongoing on detailed design and preparation of tender documents is underway.

BLARNEY VILLAGE CYCLE ROUTE Procurement of consultant is underway.

LEE TO SEA CYCLE ROUTE STUDY Procurement of consultant is underway.

MAYFIELD TO GLEN CYCLE ROUTE Route option assessment is continuing.

DOUGLAS TO GRANGE BRIDGE Tender process to appoint consultant is underway.

DONNYBROOK HILL PEDESTRIAN UPGRADE SCHEME Detailed Design is ongoing.

STREETSCAPE RENEWAL OF COOK STREET, PRINCES STREET AND MARLBORO STREET Tender process for appointment of consultant is underway.

Roads Capital Programme: CCC Funded Projects ST MARY’S CAMPUS Works completed. Project close out ongoing.

HARBOUR VIEW ROAD JUNCTION UPGRADE JUNCTION Construction is almost complete on both Harbour View Road Scheme and the additional footpath widening on the Blarney Road.

Roads Capital Programme: DTTS & CCC Funded Projects CORK SCIENCE & INNOVATION PARK ROAD PROJECT Land acquisition process is complete. Detailed Design and preparation of construction contract documents for Phase 1A is complete. Contract is ready to go to tender.

Roads Capital Programme: LIHAF Funded Projects DOCKLANDS TO CITY CENTRE PROJECT (€6.5 million) Detailed design process underway. Legal Team review of documents is complete. Design team revising documents as per Legal Team advice. Revised Part 8 publication by year’s end. GLANMIRE ROADS IMPROVEMENT SCHEME Compulsory Purchase Order has been confirmed by An Bord Pleanala, Notice to Treat was issued in August for landowners for the first package of works. Notice of Entry was issued in September. Procurement of a contractor for this work package is underway. Section 50 applications for new bridges are awaiting OPW approval and detailed design is continuing. A Section 38 consultation for alternative Cycle route connecting Rivertown to Glanmire Community College has been approved by Council.

MONAHAN ROAD EXTENSION (€5 million) Preliminary design is complete. Land Acquisition requirements have been confirmed. Site Investigation contract is complete. Part 8 planning is approved. Fencing contract procurement underway.