CE Management Report November 2021

Housing Progress Report November 2021 Schemes in Construction Scheme No. of Unts

Status *Estimated completion dates subject to change due to covid-19

Scheduled Completion Date

Aspen Drive

29

Completed

-

Blarney Street

25

Completed

-

Phase 2A

47

Completed

-

St John’s Well

6

Completed

-

Deanrock

66

Completed

-

White Street

43

Completed

-

High Street

9

Completed

-

Farranferris (AHB: Tuath)

86

Practical Completion

-

Millerd Street (AHB: Respond)

25

Completed

-

Clarendon Brook, Douglas

36

Completed

-

29 & 30 Lower John Street

17

Completed

-

Woodfield, Blarney (An Cuilleog)

18

Completed

-

Grattan Street (AHB: Good Shepherd Cork) St. Joachim and Annes (AHB: Cork Simon)

33

Completed

-

8

Completed

-

166 Sundays Well Road (AHB: Galtan)

1

Completed

-

5/6 Shandon St/9 John Philpott Curran St

9

Completed

-

Coolroe, Ballincollig (AHB: Respond)

44

Completed

-

Ballinglanna (Part V – Phase 1)

16

Completed

-

Kerry Pike (AHB: Cluid)

22

Completed – phase 1 on CBL, phase 2 April

-

Gerald Griffin Street

12

Construction completing

-

Ballinure Road

5

Completed

-

Lehenaghmore, Togher (Part V)

50

Completed

-

Madonna House – Phase 1

16

Phase 1 (from Cork County Council)

Q1 2021

Recent Completions:

623

Redforge Road (AHB: Respond)

80

Construction underway Phased Delivery from Q1 2021

Dec-21

Corkeran’s Quay

3

Construction underway

Dec-22

Phase 2C – CNWQR

24

Construction completing

22

Dec-21 with interim phasing

Boherboy Road

153

Construction underway

Gerald Griffin Street/Burkes Avenue

49

Enabling works complete. Main contract at tender stage

Jun-23

25