CE Management Report November 2021

Respond – Thomas Davis Street

28

Construction underway. Enabling Works complete

Dec-22

Boyces Street

51

Construction underway

Nov-22

Green Lane, Blackpool (AHB: Cluid)

112

Enabling Works completed. Construction underway

Dec-22

Springville House (AHB: Tuath: Downsizing)

35

Construction underway

Jan-22

Coach Street

12

Construction underway

Mar-22

Spring Lane

8

Construction underway

Mar-22

Shanakiel

20

Construction underway

July-22

Watercourse Road

37

Construction underway

Sept -22

Montenotte – Affordable Housing Scheme

27

Construction underway

Oct-22

Montenotte – Social Housing (Tuath)

27

Construction underway

Oct-22

Pouladuff Road

11

Construction underway

Jul-22

Heathfield Ballincollig (Part V)

21

Under Construction

Phased delivery Phased delivery

Ballinglanna (Later phases)

27

Under Construction

Evergreen Road (AHB: Respond)

28

Under Construction

Sept-22

Former Glenanaar Bar (AHB: Respond)

27

Under Construction

Sept-22

Part V and Turnkeys across the city

245

Construction underway. (Pre-Contract)

Various

Barrack Street

32

Under Construction

Apr-23

Wood Street

16

Under Construction

Nov-22

Cluain Ard, Blarney (Part V)

10

Construction completing

Heathfield, Ballincollig (Part V)

8

Construction completing

Coppengers Field Ballyvolane (Part V)

7

Construction completing

Skehard Road

16

Under Construction

May-22

Sarsfield Road/Doughcloyne

65

Construction underway

Phased delivery

Sunview (Downsizing)

25

Construction underway

Oct-22

Hawkes Road, Bishopstown

64

Construction underway

Aug-23

Old Mallow Road

54

Construction underway

Jul-23

Glen Ryan Road

9

Construction underway

Total Under Construction:

1,331

Schemes at Contract Award (to go to construction Q1 2022)

Scheme

No. of Units

Status

Denroches Cross

43

At contract award stage

Total:

43

26