Infrastructure Projects

Roads Capital Programme: TII Funded Projects: N40 SARSFIELD & BANDON ROAD FLYOVER PROJECT (€31.55 million) Localised settlement issues on the N40 continue to be monitored. SIAC Ltd has completed significant repairs. The Maintenance Contract for the N40 has now passed to Egis Lagan and TII. LOWER GLANMIRE ROAD RESURFACING & FOOTPATH REPAIR CONTRACT (€2.5 million) Const ruction is substantially complete with some minor works such as lining, signage and cycle protection measures to be installed in the coming weeks.

WESTERN ROAD RESURFACING AND FOOTPATH REPAIR CONTRACT (€700K) Construction tender documents are complete and the construction tender process id underway.

Roads Capital Programme: NTA Funded Projects:

CORK CYCLE NETWORK: PHASE 3 – BALLYVOLANE INCLUDING FOX & HOUNDS JUNCTION (€4.0 million) Consultants appointed. Preliminary design works underway

SKEHARD ROAD - PHASE 2 PARKHILL TO CHURCH ROAD JUNCTION INCLUDING CSO JUNCTION (€3.5 million) Construction contract is complete.

SKEHARD ROAD- PHASE 3 CHURCH ROAD TO BESSBORO JUNCTION (€2 million) appointment of contractor is underway.

DENNEHY’S CROSS TO WILTON GARDENS (€4 million) Preliminary design is complete. Part 8 planning proposals were not approved. Discussions are ongoing with the NTA concerning the delivery of the complete corridor project as part of the Cork Bus Connects Project PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 1 (Mahon to Docklands) (€2.5 million) Preliminary Design is complete. Part 8 Planning is approved. Detailed design process is underway. Site investigation contract is complete. Construction tender scheduled to be published in Q4 2020.

PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 2 (Mahon to Passage) (€4.0 million) Design Team appointment complete. Preliminary design is underway.