CE Management Report December 2020.pdf

COACH HILL Preliminary layout design is under development .

MAHON TO CITY CENTRE TRANSPORT CORRIDOR will be delivered as part of bus connects.

EXISTING NORTHERN RING ROAD ENHANCEMENT PROJECT will be delivered as a part of bus connects.

CITY CENTRE PUBLIC TRANSPORT IMPROVEMENT SCHEME Completed. Final account was agreed at the end of November.

MCCURTAIN STREET PUBLIC TRANSPORT IMPROVEMENT SCHEME work ongoing on detailed design.

SOUTH QUAYS PUBLIC TRANSPORT IMPROVEMENT SCHEME Option assessment is ongoing.

GRANGE TO TVP PEDESTRIAN & CYCLEWAY inc. N40 Bridge detailed design is underway. Ground Investigation contract is now completed. SOUTH DOUGLAS ROAD JUNCTION Part 8 approved by Council 14/12/2020. Procurement of consultants underway for detailed design.

BALLYBRACK CYCLE SCHEME work commenced on detailed design.

PEDESTRIAN SAFETY INTERVENTIONS 2019 (€500K) construction completed.

PEDESTRIAN SAFETY INTERVENTIONS 2020 (€500K) Construct ion has commenced for Vicar’s Road and will follow for onto, Dublin Hill, Ringmahon Road and Rathmore Road. Detailed design underway for St. Patrick’s Road. NORTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT. Design Team appointed for the route selection assessment. Discussions ongoing with adjoining developers/land owners Re SHD’s and requirements for set aside lands.

SOUTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT Design Team has been appointed for the route selection assessment.

CURAHEEN TO CARRIGROHANE FOOTPATH AND CYCLE PATH UPGRADE (600k) Contractor has been appointed works will commence in early January.

Roads Capital Programme: CCC Funded Projects: ST MARY’S CAMPUS works are completed. Final account discussions are underway.

HARBOUR VIEW ROAD JUNCTION UPGRADE Construction works ongoing.

DEANROCK Construction is substantially complete.

Roads Capital Programme: DTTS & CCC Funded Projects: CORK SCIENCE & INNOVATION PARK ROAD PROJECT Land acquisition process is complete. Detailed Design and preparation of construction contract documents for Phase 1A is complete. Roads Capital Programme: DUCGS & NTA Funded Project: MARY ELMES PEDESTRIAN & CYCLE BRIDGE (€5.2 million) The bridge project is complete. The repaving of Harley’s Street is complete. Project close out is underway including completion of final snags. Roads Capital Programme: LIHAF Funded Projects: DOCKLANDS TO CITY CENTRE PROJECT (€6.5 million) Detailed design process underway. Revised planning documents are under review by Legal Team. GLANMIRE ROADS IMPROVEMENT SCHEME Compulsory Purchase Order has been submitted to An Bord Pleanala, oral hearing was postponed from 20 th of April now due to take place in Q1 2021. Section 50 applications for new bridges are awaiting OPW approval and detailed design is continuing. A section 38 for traffic calming Brooklodge Grove is currently out for consultation. MONAHAN ROAD EXTENSION (€5 million) Design Team has been appointed. Preliminary design work is underway. Land Acquisition requirements have been confirmed. Urban Regeneration & Development Fund: EASTERN GATEWAY BRIDGE The draft appraisal brief & related tender documents as per DPER Public Spending Code requirements are complete. The Appraisal tender documents will be issued to the NTA & LDA for their input prior to publication. Considering options re. the incorporation of bridges and roads into one planning process. BEAMISH & CRAWFORD QUARTER INFRASTRUCTURE The appraisal process for the selection of the bridges at Proby’s Quay and Crosses Green is progressing as is the detailed design for the public realm enhancement o f South Main Street, Tuckey Street, Proby’s Quay, Sullivan’s Quay, etc. MARINA PARK PHASE 2. Preparation of design team brief and other related documents is complete. Bridge Repair and Rehabilitation Projects: DALY’S BRIDGE: Bridge re-opened for public use on 19 th December 2020.