CE Management Report May 2021.pdf

Schemes at Contract Award (to go to construction Q2/Q3 2021)

Scheme

No. of Units

Status

Hawkes Road, Bishopstown

67

At contract award stage

Denroches Cross

43

At contract award stage

Skehard Road

16

At contract award stage

Glen Ryan Road

9

At contract award stage

Old Mallow Road

57

At contract award stage

Sunview (Downsizing)

25

At contract award stage

Total:

217

Regeneration Schemes

Scheme

No. of Units

Status

CNWQR

38

Phase 2B – Tenders due back July 2021

CNWQR

41

Phase 1C – Tenders due back July 2021

Phase 1D West – Croppy Boy – AHB (Tuath) development of 21 units commenced construction in November 2019 with 7 units delivered in June 2020. Remaining units to be delivered in 2021.

CNWQR

21

Phase 1D East - Planning application submitted for Affordable Housing to be delivered by O Cualann AHB (17 units). Estimated on site by August 2021

CNWQR

17

CNWQR

62

Phase 3B – Progress to part 8 by July 2021

CNWQR

43

Phase 4A – Progress to Part 8 by August 2021

Total:

222

Capital Assistance Scheme (Construction schemes in planning)

Scheme

No. of units

Status

Respond - St Vincent’s Convent, St. Mary's Road

25

Pre-planning underway

Total:

25

25