Schemes in the Course of Planning

Scheme

No. Of Units

Status

Bramble Cottages

5

Part 8 approved

Glenamoy Lawn

3

Part 8 approved

Errigal Heights

34

Part 8 application advertised

Foyle Avenue (incl Ardmore Avenue)

3

Stage 4 submission made to the DHLGH

Madonna House - Phase 2

6

Part 8 application advertised

Poulavone, Ballincollig

64

Part 8 approved. Target date for tender: July 2021 and site start 2021

Kerry Road (Sli Gartan), Mayfield

1

Part 8 approved

Hollywood Estate

7

Part 8 approved

Wolsey Court

49

Part 8 approved. At final tender stage

Redemption Heights

64

Part 8 stage

Cloverhill Court

51

Part 8 application Q3 2021

Westside

32

Part 8 application Q3 2021

Total:

319

Capital Works Members will be aware that the Department of Housing, Local Government and Heritage (DHLGH) announced delivery targets under the Rebuilding Ireland Action Plan for Housing & Homelessness across a range of housing programmes. Cork City Council successfully met and exceeded its target for 2019 and 2020, with a total of 1,096 homes delivered in that two-year period jointly by the Local Authority and AHB Sector under their Build, Acquisition and Leasing delivery programmes. The Covid-19 pandemic has necessitated the Government mandated shutdown of construction sites in two critical periods in both 2020 and 2021 which has had an effect on programme delivery dates, however, there remains a strong construction programme pipeline which can be summarised as follows:

Construction:

Competitive Dialogue Procurement - Cork City Council placed a contract notice on the E Tenders website and the OJEU (Official Journal of the European Union) to procure innovative solutions to meeting housing targets under the Social Housing Strategy (SHS) including the construction and completion of housing projects under a parallel site acquisition and development agreement with the City Council, using a Competitive Dialogue procurement process. In Phase 1 of Competitive Dialogue, 11 schemes comprising 215 homes have progressed with the approval of the DHPLG. Construction has been completed on 7 schemes at Blackrock, Tramore Road, Ard Aoibhinn, High Street, Blarney Street & White Street totalling 159 homes. Construction continues on 2 other schemes consisting of 8 units and a further two schemes at Barrack Street and Woods Street consisting of 48 units have now commenced construction.

26