Roads Capital Programme: CCC Funded Projects: ST MARY’S CAMPUS works are completed. Final account discussions are underway.
HARBOUR VIEW ROAD JUNCTION UPGRADE Contractor appointed and works have commenced on Blarney Road end of the scheme.
DEANROCK Construction progressing.
Roads Capital Programme: DUCGS & NTA Funded Project: MARY ELMES PEDESTRIAN & CYCLE BRIDGE (€5.2 million) The bridge project is complete. The repaving of Harley’s Street is complete. Project close out is underway including completion of final snags. Roads Capital Programme: LIHAF Funded Projects: DOCKLANDS TO CITY CENTRE PROJECT (€6.5 million) Detailed design process underway. Revised planning documents are under review. GLANMIRE ROADS IMPROVEMENT SCHEME Compulsory Purchase Order has been submitted to An Bord Pleanala, oral hearing was postponed from 20 th of April due to restrictions surrounding Covid 19. New date is awaited for Q1 2021 Section 50 applications for new bridge are awaiting OPW approval and detailed design is continuing. A section 38 for traffic calming Brooklodge Grove is currently out for consultation. MONAHAN ROAD EXTENSION (€5 million) Design Team has been appointed. Preliminary design work is underway. Land Acquisition requirements have been confirmed. Urban Regeneration & Development Fund: EASTERN GATEWAY BRIDGE The draft appraisal brief & related tender documents as per DPER Public Spending Code requirements are complete. The Appraisal tender documents will be issued to the NTA & LDA for their input prior to publication. Considering options re. the incorporation of bridges and roads into one planning process. BEAMISH & CRAWFORD QUARTER INFRASTRUCTURE The appraisal process for the selection of the bridges at Proby’s Quay and Crosses Green is progressing as is the detailed design for the public realm enhancement of South Main Street, Tuckey Street, Proby’s Quay, Sullivan’s Quay, etc.
MARINA PARK PHASE 2. Preparation of design team brief and other related documents is complete.
Bridge Repair and Rehabilitation Projects: DALY’S BRIDGE: Revised arrangements in place for project close out. It is anticipated that the bridge will re-open for public use on 19 th December.
BANNOW BRIDGE, GRANGE ROAD BRIDGE, BLACKSTONE BRIDGE & HEALY’S BR IDGE: Design Team appointed . RfT advertised for the appointment of a Contractor.
PRINCIPAL INSPECTIONS OF BRIDGE AND CULVERT STRUCTURES WITHIN CORK CITY BOUNDARY 2020: Engineering consultant (WS Atkins) appointed. Inspections 80% complete.
New Cycle Lanes: HORGANS QUAY Construction of the inbound cycle lane is substantially complete. CENTRE PARK ROAD Construction of the outbound cycle lane is substantially complete.
MONAHAN’S ROAD Construction of the inbound cycle lane is substantially complete.
SOUTH MALL Contractor has been appointed.
VICTORIA ROAD, ALBERT QUAY & TERENCE MACSWINEY QUAY Construction tender process is underway. Contractor to be appointed in January 2021.
DONOVAN’S ROAD, COLLEGE ROAD, MAGAZINE ROAD TO GLASHEEN LINK Detailed design is complete for Donovan’s Rd and College Rd. Design ongoing for Melbourne Rd and Magazine Link. Construction of Donovan’s Rd and College Rd to commence in December.
MELBOURN ROAD AND ROSSA AVENUE Contractor is appointed.