Holiday World is Ireland's largest travel exhibition, featuring over 500 exhibitors from around Ireland and internationally. The Cork City stand was overseen by staff from Cork City Council and attractions in Cork City, who provided information and insider tips for a visit to Cork to some of the 45,000 visitors who attended the fair over the 3 days.

Housing Directorate __________________________________________________________________________________________________ Housing Progress Report January 2020 Schemes in Construction:

No. of Units

Completed to date

Scheme

Balance

Status

Estimated Completion

Phase 1B - CNWQR

29

29

0

Construction completed.

Nov-17

Sheridan Park

28

28

0

Construction completed.

Feb-17

Marble Lane, Ballinlough

4

4

0

Construction completed.

Jan-18

Galtan CLG – Construction completed.

124 Lower Glanmire Road

4

4

0

Jan-18

Galtan CLG – Construction completed.

2 St. Joseph’s Villas

4

4

0

Jul-18

1 Montenotte View

3

3

0

Galtan CLG – Construction completed.

Jul-18

166 Sundays Well Road

4

3

1

Galtan CLG – 3 units completed in 2018, 1 remaining to be delivered 2019.

Dec-19

Sheridan Court

3

3

0

Construction completed.

Feb-18

Church Road

43

43

0

Construction completed.

Oct-18

Ard Aoibhinn, Mayfield - Phase 1

5

5

0

Construction completed.

Oct-18

37-39 Dublin St

5

5

0

Construction completed.

Aug-18

28-29 Dublin St

10

10

0

Construction completed – Respond.

Sep-18

Ceanncora Lawn

1

1

0

Construction completed – Cork Mental Health Association. Phase 1 completed (31 units). Tuath Housing Association.

Aug-18

The Meadows Phase 1

31

31

0

Dec-18

The Meadows Phase 2

21

21

0

Practical completion

Dec-19

The Meadows Phase 3

17

17

0

Practical completion

Dec-19