Infrastructure Projects __________________________________________________________________________________________________ Roads Capital Programme: TII Funded Projects:
LOWER GLANMIRE ROAD RESURFACING & FOOTPATH REPAIR CONTRACT (€2.5 million) Construction is substantially complete with some minor works such as lining, signage and street furniture to be installed in the coming weeks.
N40 SARSFIELD & BANDON ROAD FLYOVER PR OJECT (€31.55 million) Localised settlement issues on the N40 continue to be monitored. SIAC Ltd has completed significant repairs. The Maintenance Contract for the N40 has now passed to Egis Lagan.
Roads Capital Programme: NTA Funded Projects: CORK CYCLE NETWORK: PHASE 3 – BALLYVOLANE INCLUDING FOX & HOUNDS JUNCTION (€4.0 mill ion) Consultants appointed. Option assessment and data collection underway
MAHON TO CITY CENTRE TRANSPORT CORRIDOR (€5 million) Procurement documents for the appointment of a design team are with NTA for approval to proceed. EXISTING NORTHERN RING ROAD ENHANCEMENT PROJECT Procurement documents for the appointment of a design team are under development. CITY CENTRE PUBLIC TRANSPORT IMPROVEMENT SCHEME (€5 million) Con struction is complete. Final Account discussions are ongoing. MCCURTAIN STREET PUBLIC TRANSPORT IMPROVEMENT SCHEME (€8 million) Preliminary Design is ongoing. Awaiting NTA approval to proceed to Part 8. SOUTH QUAYS PUBLIC TRANSPORT IMPROVEMENT SCHEME (€4. 5 million) Consultants appointed. Data collection and option assessment is underway.
SKEHARD ROAD - PHASE 2 PARKHILL TO CHURCH ROAD JUNCTION INCLUDING CSO JUNCTION (€3.5 million) Construction contract is complete. Snagging work is ongoing. SKEHARD ROAD- PHASE 3 CHURCH ROAD TO BESSBORO JUNCTION (€2 million) Detailed Design is ongoing. The process for Land Acquisition is underway. 7 of the 12 properties are now agreed. DENNEHY’S CROSS TO WILT ON GARDENS (€4 million) Preliminary design is complete. Part 8 planning proposals were not approved. Discussions are ongoing with the NTA concerning the delivery of the complete corridor project. PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 1 (Mahon to Docklands) ( €2.5 million) Preliminary Design is complete. Part 8 Planning is approved. Procurement of Design Team is complete. The detailed Design process is underway. PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 2 (Mahon to Passage)(€4.0 million) Preparation o f tender documents for selection of Design Team is progressing. LEHENAGHMORE ROAD WIDENING & REALIGNMENT PROJECT Preliminary design layout drawings are under development. Funding discussions with the NTA is underway.
GRANGE TO TVP PEDESTRIAN & CYCLEWAY inc. N40 Bridge detailed design is underway.
THOMAS DAVIS BRIDGE JUNCTION IMPROVEMENT SCHEME (€450K) Construction works are complete - signalised junctions now in operation.
SOUTH DOUGLAS ROAD JUNCTION Part 8 process not completed.
BALLYBRACK CYCLE SCHEME Part 8 planning approval in place.
REPAIR OF BANNOW, HEALY’S, GRANGE ROAD & BLACKSTONE BRIDGE advertised for the appointment of a Consultant to provide Engineering Services.
CLARKE’S HILL Preliminary Design and Part 8 planning is complete. Land Acquisition discussions are underway.
COACH HILL Preliminary layout design is under development.
PEDESTRIAN SAFETY INTERVENTIONS (€5 00K) construction works are ongoing at 6 locations.
HORGANS QUAY CYCLE & PEDESTRIAN ENHANCEMENT PROJECT (€0.5 million) Design of the proposed enhancement work on Water Street and Horgan ’s Quay is progressing. Section 38 Planning will be published within the next month.
NORTHERN DISTRIBUTER ROUTE SELECTION ASSESSMENT The preparation of contract documents for the appointment of a design team to determine the route of the proposed northern distributer road is progressing.
Page | 36
Powered by FlippingBook