Heathfield, Ballincollig (Part V)
8
Construction completing
Coppengers Field Ballyvolane (Part V)
7
Construction completing
Skehard Road
16
Under Construction
Mar-22
Phased delivery
Sarsfield Road/Doughcloyne
65
Construction underway
Sunview (Downsizing)
25
Construction underway
Oct-22
Total Under Construction:
1,248
Schemes at Contract Award (to go to construction Q4 2021)
Scheme
No. of Units
Status
Hawkes Road, Bishopstown
67
At contract award stage
Denroches Cross
43
At contract award stage
Glen Ryan Road
9
At contract award stage
Old Mallow Road
57
At contract award stage
Total:
176
Regeneration Schemes
Scheme
No. of Units
Status
CNWQR
38
Phase 2B – At tender review stage
CNWQR
41
Phase 1C – At tender review stage
Phase 1D West – Croppy Boy – AHB (Tuath) development of 21 units commenced construction in November 2019 with 7 units delivered in June 2020. Remaining units to be delivered in 2021. Phase 1D East - Planning granted for Affordable Housing to be delivered by O Cualann AHB (17 units). On site Q4 2021.
CNWQR
21
CNWQR
17
CNWQR
62
Phase 3B – Part 8 due to be advertised November 2021
CNWQR
43
Phase 4A – Part 8 due to be advertised November 2021
Total:
222
23
Powered by FlippingBook