CE Management Report September 2021

Infrastructure Projects Roads Capital Programme: TII Funded Projects WESTERN ROAD RESURFACING AND FOOTPATH REPAIR CONTRACT (€1.6m) Construction of footpaths, drainage & carriageways are complete. Work on remaining asphalt and snagging is ongoing.

AIRPORT HILL PAVEMENT RENEWAL CONTRACT (€1.5m) Contractor appointed. Work expected to commence in the coming weeks. A six-week work programme.

CORK CITY NORTHERN TRANSPORT PROJECT (formerly Cork North Ring Road) Design Team for the route selection process has been appointed. Section 85 Agreement is being prepared. Route selection process will be concluded by the end of 2023. Project website, logo, name have been agreed with TII & Project Team. Strategic Assessment Report (SAR) submitted to Department of Transport prior to DPER.

M/N20 CORK LIMEICK MOTORWAY Route selection process is underway. Selection of the preferred route is expected in the New Year. Project Phasing being considered.

N40 SARSFIELD & BANDON RD FLYOVER PROJECT Settlement of the pavement continues to be monitored. The Contractor has undertaken several repairs and has agreed to complete other repairs to the pavement where cracking & settlement has occurred. Roads Capital Programme: NTA Funded Projects CORK CYCLE NETWORK: PHASE 3 – BALLYVOLANE INCLUDING FOX & HOUNDS JUNCTION Preparation of Part 8 documentation is underway.

SKEHARD ROAD- PHASE 3 CHURCH ROAD TO BESSBORO JUNCTION Construction ongoing.

MCCURTAIN STREET PUBLIC TRANSPORT IMPROVEMENT SCHEME Procurement of the contractor for main works is underway. Advance works contract is at construction. PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 1 (Mahon to Docklands) C onstruction ongoing. Phase 1 (The Marina to Blackrock Station) has reopened. Phase 4 (N40 to Mahon) has reopened. The contractor is now working on Phase 2 (Blackrock Station to Skehard Rd). The new pedestrian/cycle bridge will be lifted into place in the coming two weeks. PASSAGE GREENWAY ENHANCEMENT CONTRACT Phase 2 (Mahon to Passage) (€4.0 million) First round of early consultation is concluded. Design of the preferred route is complete. Planning to commence before years end. LEGHENAGHMORE ROAD WIDENING & REALIGNMENT PROJECT Design Team is appointed. Part 8 planning is approved. The project requires land acquisition (28 distinct plots). Valuation negotiations ongoing. CLARKE’S HILL Design and planning is complete. Land Acquisition discussions are underway. Negotiations are ongoing re. part funding of the project with TII.

COACH HILL Preliminary layout design is under development .

MARINA PROMENADE Procurement of design team is complete. Prelim Design is progressing.

STREETSCAPE RENEWAL OF DOUGLAS ST, MARY ST & WHITE ST Tender documents for the selection of multidisciplinary design team is under development. MAHON CYCLE ROUTE Preliminary Design is complete. Part 8 documents under development.

KILCULLY & UPPER GLANMIRE PEDESTRIAN IMPROVEMENT SCHEME Preliminary design is complete. Consultation with residents’ groups is ongoing. Design Consultants have been appointed.

GLANMIRE TO CITY CYCLE NETWORK (Phase 1 Glanmire to Dunkettle) Design Team appointed. Prelim Design is underway.

MAHON TO CITY CENTRE TRANSPORT CORRIDOR will be delivered as part of bus connects.

EXISTING NORTHERN RING ROAD ENHANCEMENT PROJECT will be delivered as part of bus connects.

SOUTH QUAYS PUBLIC TRANSPORT IMPROVEMENT SCHEME Option assessment is ongoing.

GRANGE TO TVP PEDESTRIAN & CYCLEWAY inc. N40 Bridge Procurement of contractor to commence early October. Compulsory Acquisition Order confirmed by An Bord Pleanala for required land acquisition. Notice to Treat issued in September.

SOUTH DOUGLAS ROAD JUNCTION Detailed design and preparation of tender documentation is being finalised. Tender package for appointment of contractor issued end of September.